Tag: blackout

  • Blackout imminent in Akure, Ado-Ekiti

    Blackout imminent in Akure, Ado-Ekiti

    •Transmission Company of Nigeria cries out for help

    Electricity consumers in Akure, Ondo State and Ado-Ekiti in Ekiti State could face total blackout from the Osogbo region of the Transmission Company of Nigeria (TCN), following a fire that engulfed a major transformer that supplies the two cities and two other major cities in Osun State.

    The 4TI 150MVA transformer which got burnt on March 7, this year is yet to be repaired or replaced, a development that had adversely affected power supply to not just the two cities, but also Ilesa and Ile-Ife in Osun state.

    And to avert a major blackout in most of the Southwest states under its jurisdiction, the Osogbo TCN, which is also strategic to transmitting power to some other parts of the country, including some neighbouring countries has called for increased funding and overhauling of its ageing equipment, some of which had been in use since 1968.

    Speaking recently during a facility tour of the company’s operation by the governing board, the General Manager (Technical), Vincent Aligwara said, adequate funding had become necessary to avoid system collapse

    According to him, the Osogbo transmission region like other regions is facing a myriad of challenges, including paucity of fund, aging 132KV lines, lack of operational vehicles and most recently, replacement of the 4T1 150MVA transformer that got burnt at Osogbo. The transformer is yet to be replaced, a development he lamented had adversely affected power supply to areas like Ado-Ekiti, Akure, Ondo, Ife and Ilesa.

    The General Manager said that the company’s corporate headquarters was making arrangement to use another transformer earlier earmarked for reinforcement to replace the burnt one to make the station return to the status quo before the March 7 incident.

    Reeling out some of the other problems confronting the region, Aligwara said: “Some of our 132KV lines were constructed long time ago. In this regards, Osogbo-Akure and Ayede-Sagamu are mostly affected. These lines are not loaded optimally and as result can snap. The Osogbo-Akure line is more critical because it supplies two state capital cities – Akure (Ondo State) and Ado-Ekiti (Ekiti State). Work centres and sub-regions under Osogbo region lack healthy vehicles to effectively meet up with the increasing challenges of maintaining the sub-station equipment and transmission line patrol. We have been on minimal funding for a very long time. Our funding is not based on the present economic realities and no business can thrive when economic indices are ignored. A typical example is the unstable fuel crisis. Within Osogbo region, a litre of PMS sells for between N110 and N140”.

    The chairman of TCN Osogbo region’s Senior Staff Association of Electricity and Allied Companies, Comrade Samuel Alade, and secretary of the National Union of Electricity Employees in Osogbo region, Comrade Mudasiru Adeniyi, implored the board to intervene and address some of the challenges facing the company.

    Responding, the leader of the visiting team, Prof. Peter Akpe, who is the chairman of the TCN board, assured that their complaints would receive urgent attention. He said that the board recently met and discussed the challenges of the company with the Vice President, Namadi Sambo, assuring that in the next two weeks they would be able to access fund to effect a positive change in the power sector.

    The Osogbo region has two sub-regions – Ayede (Oyo State) and Osogbo (Osun State), as well as two work centres – Omotoso (Ondo State) and Ganmo (Kwara State).

    The region, which falls within the grid triangle of Benin, Osogbo and Lagos, no doubt, is critical to the national grid. The stability of the grid, to a large extent, depends on the security of this axis and Osogbo region sits at its centre.

  • Disengaged PHCN workers threaten blackout over severance pay

    Disengaged PHCN workers threaten blackout over severance pay

    Electricity workers under the aegis of the National Union of Electricity Employees (NUEE), have threatened blackout the entire country if the Federal Government fails to settle their entitlements.

    NUEE General Secretary, Comrade Joe Ajaero, who this in Jos yesterday, said the union has uncovered a plot by the government to use the military to eject its members from office, warning that “any station the Federal Government moves in with force, without settling labour issues, should be shutdown.

    “We have been patient enough and we cannot continue to be patient while they are driving us to the grave. I am saying that enough of this provocation,” stressing that no amount of “military presence will make us to abandon our entitlement, because it is not by power or might. We are not going to get there with gun or knife, but the soldiers will be there and there will be darkness in this country.

    “They have even written letters, when they come with those military men. Unfortunately, those signing those letters are not the people that employed you; I told them that one has legal implication.”

    Ajaero said that PHCN staff were yet to receive their pension component, saying it was unfortunate that the public is being misinformed that PHCN staff have been paid about N400billion entitlements they are being owed.

    Ajaero, who is also the Deputy National President of Nigeria Labour Congress said, the government spent $11billion in constructing the power plants and $16billion was spent on the same power plants during the regime of former President Olusegun Obasanjo, but unfortunately the power plants were sold for $3billion.

    Also speaking the Secretary of NUEE North-East zone, Anthony Sule, said, “As I speak to you, I cover North-East zone, no worker in both Jos Zonal Office and Jos Business Unit has been paid, incidentally Jos Business Unit is about the largest in this zone, all the other business units of Benue, Gombe and Bauchi there are still pockets of payments left undone.

  • ‘How govt  can reduce power blackout’

    ‘How govt can reduce power blackout’

    Foluseke Abidemi Somolu, an engineer and former topshot at the defunct National Electric Power Authority (NEPA), was Senior Special Assistant (Power Sector Reform) to Presidents Olusegun Obasanjo and Umar Yar’ Adua. Somolu, in this piece, sheds light on why the country sometimes experiences power blackout, among others.

     

    System collapses in the Nigerian power supply system have been reported in the newspapers. Up to thirteen have been reported this year alone, as at 1st of August. But what is a system collapse, what are the consequences, etc.?

    ‘System collapse’ is the term used to describe the situation when all the power generating stations connected to the grid shut down at the same time or immediately one after the other, leaving the entire area supplied by the grid (the whole country, in the case of the Nigerian grid) in blackout. Generating plants may shut down as a result of human deliberate control action as part of normal operational scheduling, or automatically as a result of self-protective action.

    Self-protective shutdown of generators may be initiated by protective relays installed on the generating plant reacting to any one or combination of potentially harmful operational development within the power station or individual generator. It may, on the other hand be as a result of happenings on the grid, external to the generating plant, but which have the potential to impose operational duties on the generator beyond its capability. One of such is when the system operating frequency falls outside the allowable deviation from the nominal level stipulated for the generating plant. The system nominal frequency applicable to all generating plant and electrical appliances in Nigeria and many other countries is 50Hz (50 cycles per second). (The exceptions are in the Americas, north and south, where it is 60Hz). Thermal stations (i.e. those burning some form of fuel, especially the steam stations), due to their many pumps and motors controlling critical functions, are more sensitive to low frequency than hydro stations. But all of them, whether hydro or thermal, will eventually shut down when the frequency falls low enough, and then a system collapse results.

    We may ask what causes the system frequency to fall. A load demand imposed on the grid greater than the combined capacity of all the connected generating stations will cause the system frequency to fall. With our low generating capacity (4000MW) in comparison to our country’s actual demand, it is obvious we will always be operating in the vicinity of low system frequency. When the increase in load demand is due to consumers, the rate of fall in the system frequency is gradual and the speed governors of each generator can take some corrective action automatically by boosting the fuel input to the generator to increase its speed, and hence the frequency, provided the generator had not been fully loaded up to that point. This is similar to when, upon approaching a hill, the driver of a truck changes gear and presses down harder on the accelerator pedal of the truck. Good system operating practice requires that one or more generators in the grid are deliberately only partially loaded so there is ample and readily available spare capacity, called “spinning reserve”, to absorb unplanned sudden load demand placed on the grid such as when a huge industrial consumer comes on line, or a generating plant is shut down by its own self-protective action thereby placing a heavy load demand on the remaining generating stations. When these automatic actions, i.e. the combination of the speed governors and the spinning reserve, fail to arrest the frequency drop, the system operators at the National Control Centre who are monitoring the state of the power system and noticing the dropping system frequency, can intervene ‘manually’ and instruct one or more power stations to start and bring up additional generating plant. They can in addition instruct a substation to disconnect some consumers to reduce the system load demand. Nowadays the system operators are not able to establish communication with stations quickly enough to arrest the impending collapse. This is because the SCADA (i.e. Supervisory Control and Data Acquisition) that enables the system operator monitor happenings at all grid stations, as well as the special “no fail” communications facilities built for instant linkup between the control centre and all stations when the grid was being developed in 1960s -1980s and which were still functioning up to the mid 1990s, are all now virtually broken down or not even there anymore. The voice communications have been largely replaced with GSM phones but their ‘network problems’ and ‘subscriber not available’ messages, and other interruptions obviously make the use of GSM completely unsuitable for this function.

    Another scenario in which the system frequency falls is when the system overload is caused by a fault (i.e. a short-circuit) on any one of the many transmission lines that make up the grid. Since many thousands of kilometers of our transmission lines pass through heavy forests, the possibility of vegetation fouling the lines and causing faults is ever present, except the line trace is cleared of all vegetation up to 15metres on either side of the line for the whole length of the line, which is easier said than done, especially because of the heavy costs and logistics involved. These line faults represent very heavy load demands that require every generating plant on the grid to contribute multiples of its capacity, which of course, is impossible. Here we have a “double jeopardy” situation. Apart from the overload placed on each generator, which is harmful on its own, the system frequency also drops very sharply and beyond allowable thresholds. The system protective relays should normally remove the faulted line from service promptly before the generators’ self-protection relays react. But they can only do so, if they act in a coordinated manner, i.e. if they are properly calibrated and their settings coordinated with each other, and also provided the communications links between them are functioning. Again it is doubtful if this is still so nowadays. Protection engineers, specialists in their own right, whose function it is to calibrate and ensure proper coordination of these relays are an endangered species in the power industry nowadays. Also, as has been mentioned earlier, most tele-protection communication channels in the power system are no more functioning as they used to. Line faults are therefore usually removed too slowly. The ‘last ditch’ provision to save the system from collapse in this situation then is the under-frequency emergency load-shedding arrangement. But it is not always very effective because the consumers on the feeders it removes from service may not have their total load anywhere close to the demand imposed on the system by the fault, and a system collapse still occurs.

    Now why do blackouts due to system collapses last so long? The major problem encountered during restoration following a system collapse is the time required to restart the generating plants. The thermal stations pose the biggest challenge. They cannot remain spinning when they have no load connected to them and usually shut down when system collapses occur. And when they shut down, they eject their steam they have built up and depend upon to operate. This is in order to avoid dangerous steam pressure buildup. It takes about six to ten hours to raise new steam and start operation again. And when they are restarted, they have to be loaded in small increments, allowing them to stabilise at each load level before taking on additional consumers. Sometimes the anxiety to load the generators quickly and shorten the system blackout may lead to taking on too much load at a time and cause a generator to shut down again and return the operators to the beginning all over again. All this while, the national control centre (NCC) is abuzz with activities, talking to and passing instructions to all the power stations and grid-connected substations across the country, coordinating the restoration efforts.

    Even as simply as one has tried to describe it, the foregoing should have shown that maintaining the integrity of the grid consists of a series of many and painstaking activities, many of them highly specialised. It also requires the continuous availability of many facilities for the operators of the grid, as has been mentioned earlier, over and above simply building of power stations and substations in various parts of the country, and transmission lines to link them to each other. These facilities include but are not limited to the Supervisory Control and Data Acquisition (SCADA) and no-fail voice communications that must work even in the face of national power blackout.

    And having made this point, one should also add that while it may not be possible to totally avoid system collapses, their frequency can definitely be drastically reduced. In fact, in 1992 the country recorded zero system collapses. In the few years preceding that year (1992), through the determined efforts of the staff and the cooperation of Management (through the provision of funds), the coordination of the protective schemes in the grid was highly improved, most of the inconsistencies in the relay settings having been ‘debugged’; the SCADA having just been commissioned and put to use in the country’s power system for the first time, and the power system communications facilities being maintained in correct working order. Staff at that time were also very well trained to have been able to do the operation and maintenance work required at the highest standards. So, if we really want to reduce or eliminate system collapses, government needs to look into all these.

     

  • Students protest blackout

    Students protest blackout

    OAU students last Friday night took to the roads on the campus to protest a black-out, which lasted for 48 hours. The protest, which lasted for over an hour, with witnessed by many students who left their rooms and lecture classes to express their displeasure to the management. A 500L student of Medicine, who simply identified himself as Ayo, told CAMPUS LIFE:”This is not the first time such will be happening. They refused to reinstate our Students’ Union and now they’re simply saying we can’t read. Last session, it was a four-day black-out and we all knew the implication when our results were released. Although reasons for the black- out was unknown as at the time of this report, the electricity was restored back at 9:45am on Saturday with shouts of “up Nepa!” renting the air in hostels as students rush to charge their gadgets as well as to iron their clothes.

     

  • Uzochukwu fears Afcon blackout

    Uzochukwu fears Afcon blackout

    Super Eagles’ right full-back, Ugonna Uzochukwu says he fears an Africa Cup of Nations (AFCON) blackout for domestic players due to uncertainty surrounding the league kick-off date.

    The Nigeria Premier League (NPL) season was scheduled to start on Saturday, December 1 before the latest indefinite postponement of pre-season activities by the league body.

    Uzochukwu said the scenario poses a sstrong disadvantage to the domestic players compared with their foreign-based counterparts playing competitive matches week in, week out.

    “Of course, we’re at a disadvantage for selection for the Africa Cup of Nations next January in South Africa.

    “The foreign-based players have the edge at the moment because their league season is on and majority of them play regularly every other week making it easy to assess their form.

    “We were happy when December 1 was fixed to start the season, rumour has it that it has been postponed indefinitely and now our morale has gone down once again.

    “Though we’re stepping up preparations to avoid being caught unawares, it won’t be the same if the commencement date was certain.

    “I know few domestic players will still make the AFCON list but had the league been running the opportunity would have been more. We’re now endangered species and least attractive for the AFCON for no fault of ours,” he lamented to supersport.com.

    The Enugu Rangers defensive midfielder wants Eagles’ manager, Stephen Keshi look in his direction for the batch of home lads to return to the AFCON camp next month.

    “I want another consideration when the Eagles’ gate opens next month for the final leg of preparations.

    “I still have lots to contribute to the team especially in the backline department,” he said.