Tag: grid

  • BREAKING: TCN mum as national grid collapses

    BREAKING: TCN mum as national grid collapses

    The Transmission Company of Nigeria (TCN) was quiet about the reason for the collapse of the national grid at 12:40am on Thursday.

    At 8:37am, the total power allocation to the 11 electricity Distribution Companies (DisCos) was 00:00MW.

    Its Public Affairs General Manager, Mrs. Ndidi Mbah did not answer calls from The Nation or respond to text message on why the national grid collapsed.

    The situation came after the TCN on August 29, 2023 celebrated consecutive 400 days of grid stability.

    But according to the data The Nation obtained from the Independent System Operator, there were already signs of imminent collapse as early as 10:00pm on Wednesday when virtually all the 26 electricity generation plants output declined 00MW.

    This threw the entire Nigerian Electricity Supply Industry (NESI) into a nationwide outage.

    Already, some of the electricity Distribution Companies have informed customers of the situation of the network.

    Read Also: ‘Create local grids to relieve national grid’

    For instance, in a message to its customers this morning, the Enugu Electricity Distribution Company (EEDC), said the grid collapse has resulted in the loss of supply being experience in the country.

    Its message, which its Head, Corporate Communications, Mr. Emeka Ezeh signed said: “The Enugu Electricity Distribution Company PLC (EEDC) wishes to inform her esteemed customers of a total system collapse which occurred  at 12:40am today, 14th September,2023. 

    “This has resulted to the loss of supply currently being experienced across the network.

    “Due to this development, all our interface TCN stations are out of supply, and we are unable to provide service to our customers in Abia, Anambra,  Ebonyi,  Enugu and Imo States.

    “We are on standby awaiting detailed information of the collapse and restoration of supply from the National Control Centre (NCC), Osogbo.”

    Details Shortly…

  • Nigeria’s grid power deficit hovers around 14,622Mw

    Electricity consumers connected to the national grid need additional output of 14,622megawatts (Mw) to meet their requirements, a report from the Transmission Company of Nigeria (TCN) has revealed.

    The company’s daily operational report showed that between Sunday and Tuesday this week, national peak demand forecast has been above 17,000Mw while output remains slightly above 3,000Mw.

    The report said that the national peak demand forecast was 17,720Mw while generation stood at 3,097.3Mw, reflecting a shortfall of 14,622.7Mw. Generation to the national grid, according to the report, has been about 3,000Mw since July, when attacks on gas pipelines by the Niger Delta militants started reducing.

    The TCN also said the nation has installed transmission capacity of 11,165.40Mw while the functional facilities, if optimally utilised, can supply 7,139.60Mw. The shortfall may be due to several constraints, including facility breakdown.

    Also, contrary to allegations of poor capacity leveled against the TCN, including inability to wheel more than 5,000Mw to power distribution firms, the TCN, as at Monday, said its transmission capability was 7,000Mw while the network operational capability was 5,500Mw.

    The Executive Director, Research and Advocacy, Association of Nigerian Electricity Distributors (ANED), the umbrella body of all the electricity distribution companies in Nigeria, Mr. Sunday Olurotimi Oduntan, said the estimated national peak demand forecast of about 17,000Mw by the TCN is only a fraction of the actual national demand as the huge energy-consuming firms are not connected to the grid.

    Oduntan said it was difficult to determine national consumption as most of the big consumers are off-grid. “The actual national energy demand may be difficult to determine because many organisations, industrial concerns and rural communities such as the Redeemed Christian Church and Winners chapel headquarters as well as Dangote Industries Limited, among many others, are not connected to the grid.

    “There huge power deficit in Nigeria, but going by the number of customers, currently captured on the grid, 20,000Mw would be able to give the stable electricity supply expected by Nigerians.  However, It is a herculean task to be able to generate the 20,000Mw that I feel will enable industrial firms to comfortably connect to the national grid,” he said.

  • Bresson to add 500Mw to national grid

    Bresson to add 500Mw to national grid

    Federal Government’s efforts to increase power generation has recieved a boost as Bresson Nigeria Limited is set to add 500 megawats (Mw) to the national grid next year.

    Speaking yesterday during a courtesy call on Vice President Yemi Osibajo by a team of Bresson Nigeria Limited, Prof Osinabjo told the investors that the administration is committed to removing all bottlenecks hindering investors in the power sector.  He commended Bresson for the integrated nature of its power projects, a model of fuel sufficiency by also investing in gas production.

    While assuring that the administration is working to ensure regular supply of gas to the power plants  and efforts are on to attract investment into the sector, he said Bresson integrated  model in power generation is a good model. ’’We shall support you and other genuine investors with recognisable foot print but we shall monitor you closely to ensure you adhere to your schedule,’’ he said

    Chairman of the firm,  Gbenga Olawepo-Hasim, while briefing the Vice President said the megawatts to be generated will come from Bresson Initiative and its Magboro power plant in Ogun State.

     

  • ’97m Nigerians don’t access grid electricity’

    No fewer than 97 million out of 175 million Nigerians have no access to grid electricity.  The remaining 78 million people who are connected to the grid face substantial power interruptions, the Energy Savers Nigeria, a non-governmental organisation (NGO) has said.

    In a paper titled: “The Nigerian Power Sector, A Performance Appraisal under the Buhari Administration” Moses Nasamu, a  member of Board of Trustees of Energy Savers Nigeria, said about 56 per cent of the population are connected to the grid, while 44 per cent  are not.

    He said an estimated 41  per cent of Nigerian businesses generate their own power supply to augment supply from the grid, in line  with the recent World Bank report on electricity situations in Nigeria, adding that the problem was caused by poor generation and distribution system and other systemic issues in the sector.

    It said Nigeria lags behind other developing nations in terms of grid- based electricity consumption with 126 kilowatts hour(kwh) per capita, stressing that electricity consumption is expected to be five times higher than what it is today in Nigeria, if we  consider the country’s Gross Domestic Product( GDP) alongside other countries globally.

    The paper said 25 per cent of Nigeria’s 12, 522 megawatts (Mw) of electricity installed reach the end user. “Widespread inefficiency means that only 3, 879Mw of this capacity is operational, with 3,600Mw transmitted and 3,100 distributed. Most of the shortfalls, which were about 5,381Mw, is capacity that is unavailable due to obsolete equipment and poor maintenance or due to ongoing maintenance and repair activities at existing power plants. Also, about 3,262Mw of electricity is non-operational primarily due to gas, water, high frequency, and transmission line constraints.”

    According to the paper, the sector has recorded some operational improvements, mainly driven by increased availability of gas since May 29th, 2015, when the Buhari/Osinbajo led government started.

    The paper stated that in August 2015, Nigeria hits historical highs as both peak generation and total energy generated across the system stood at 4,811Mw and 4,213 megawatts hour (mwh) respectively. It said transmission losses fell by 10 per cent between June and August 2015, compared to the first four months of the year.

    “Nigerians would recall that at the commencement of Buhari/Osinbajo’s administration in May this year, the sector was plagued with challenges,  which included under-utilisation of generating plants partly due to insufficient gas availability occasioned by  frequent vandalism of gas distribution assets, inadequate transmission infrastructure, high distribution losses, liquidity problem, among others,” the group added.

    They said electricity generation and distribution has improved relatively, despite the fact that the problems still exist in the sector. “The Buhari government has helped in restoring confidence in the sector through its decision to fast-track execution of the first set of World Bank partial risk guarantees, and granting of sovereign immunity waiver which aimed at increasing the rate of growth of the first tranche of project-financed Independent Power Projects (IPPs) and the interim execution of the contracts undertaken by the management of Transmission Company of Nigeria (TCN).

    On solution, the group urged the successor distribution companies to improve on their revenues in order to enable them fund what they described as ‘Wholesale Obligations,’ cater for their operating expenditure requirements,  invest in new and modern capacity, and ensure cost- effective tariff is provided for the teeming consumers of electricity in Nigeria.  They said when these measures are well implemented, power supply would improve and industrial activities will improve also.

  • ’97m Nigerians don’t access grid electricity’

    No fewer than 97 million out of 175 million Nigerians have no access to grid electricity.  The remaining 78 million people who are connected to the grid face substantial power interruptions, the Energy Savers Nigeria, a non-governmental organisation (NGO) has said.

    In a paper titled: “The Nigerian Power Sector, A Performance Appraisal under the Buhari Administration” Moses Nasamu, a  member of Board of Trustees of Energy Savers Nigeria, said about 56 per cent of the population are connected to the grid, while 44 per cent  are not.

    He said an estimated 41  per cent of Nigerian businesses generate their own power supply to augment supply from the grid, in line  with the recent World Bank report on electricity situations in Nigeria, adding that the problem was caused by poor generation and distribution system and other systemic issues in the sector.

    It said Nigeria lags behind other developing nations in terms of grid- based electricity consumption with 126 kilowatts hour(kwh) per capita, stressing that electricity consumption is expected to be five times higher than what it is today in Nigeria, if we  consider the country’s Gross Domestic Product( GDP) alongside other countries globally.

    The paper said 25 per cent of Nigeria’s 12, 522 megawatts (Mw) of electricity installed reach the end user. “Widespread inefficiency means that only 3, 879Mw of this capacity is operational, with 3,600Mw transmitted and 3,100 distributed. Most of the shortfalls, which were about 5,381Mw, is capacity that is unavailable due to obsolete equipment and poor maintenance or due to ongoing maintenance and repair activities at existing power plants. Also, about 3,262Mw of electricity is non-operational primarily due to gas, water, high frequency, and transmission line constraints.”

    According to the paper, the sector has recorded some operational improvements, mainly driven by increased availability of gas since May 29th, 2015, when the Buhari/Osinbajo led government started.

    The paper stated that in August 2015, Nigeria hits historical highs as both peak generation and total energy generated across the system stood at 4,811Mw and 4,213 megawatts hour (mwh) respectively. It said transmission losses fell by 10 per cent between June and August 2015, compared to the first four months of the year.

    “Nigerians would recall that at the commencement of Buhari/Osinbajo’s administration in May this year, the sector was plagued with challenges,  which included under-utilisation of generating plants partly due to insufficient gas availability occasioned by  frequent vandalism of gas distribution assets, inadequate transmission infrastructure, high distribution losses, liquidity problem, among others,” the group added.

    They said electricity generation and distribution has improved relatively, despite the fact that the problems still exist in the sector. “The Buhari government has helped in restoring confidence in the sector through its decision to fast-track execution of the first set of World Bank partial risk guarantees, and granting of sovereign immunity waiver which aimed at increasing the rate of growth of the first tranche of project-financed Independent Power Projects (IPPs) and the interim execution of the contracts undertaken by the management of Transmission Company of Nigeria (TCN).

    On solution, the group urged the successor distribution companies to improve on their revenues in order to enable them fund what they described as ‘Wholesale Obligations,’ cater for their operating expenditure requirements,  invest in new and modern capacity, and ensure cost- effective tariff is provided for the teeming consumers of electricity in Nigeria.  They said when these measures are well implemented, power supply would improve and industrial activities will improve also.

  • Minister: Kashimbila Dam ’ll add 40mw to national grid

    Minister: Kashimbila Dam ’ll add 40mw to national grid

    The Kashimbila Multipurpose Dam will add 40 megawatts to the national grid, Minister of Power Prof. Chinedu Nebo has said.

    He noted that the power generated from the dam would serve Taraba, Benue and Plateau states.

    Nebo said the hydro power components of the dam and turbines were in place for power generation.

    He spoke to reporters at Kashimbila in Tarko Local Government Area of Taraba State during a tour of the dam.

    Nebo was accompanied by the Minister of Water Resources, Mrs. Sarah Ochekpe and her Culture, Tourism and National Orientation counterpart, Mr. Edem Duke.

    He said President Goodluck Jonathan had approved a contract, which would put in place transmission sub stations and lines.

    Nebo said: “Just because of this hydro power plant, the transmission infrastructure that will be put in place will strengthen Taraba State, moving to Benue State and Plateau State so that we will have a reliable electricity grid in this part of the country.

    “For now, that is what it has been designed for. Remember that the initial plan was 10 megawatts. Then it went up to 20, to 30 and to 40. So it is maximisation of our available resources. I will say for now, 40 megawatts is ample for the volume of water that flows in this area.

    “So, evacuation is not going to be a problem. This is why we want to make sure that immediately the hydro power is ready with the transmission on course, it will not take much to do it. There will be no stranded power here at all.”