Tag: Lagos-Ibadan standard gauge

  • Lagos-Ibadan Standard Gauge: A spanner in the works?

    A mild tremor on the speed train corridor and a few adjustments to the project may alter the government’s plan to roll out the trains for commercial activity on the Lagos-Ibadan standard gauge in October, writes ADEYINKA ADERIBIGBE

    When the Nigerian Railway Corporation (NRC) Chairman, Mallam Ibrahim Alhassan, led members of the board on a tour of the Lagos-Ibadan standard gauge penultimate week, all they saw was that the Corporation appeared set for eventual roll out of commercial activity latest by October.

    But that expectation may be threatened unless the contractor rises up to the latest challenge that has confronted the project. An earth tremor that occurred at DK 44 (Kilometre 44), at a village under Ifo Local Government, last week, may throw a spanner in the works and threaten the integrity of the project.

    The Federal Ministry of Transport (FMOT) was visibly agitated by the development and its Permanent Secretary, Mr Sabiu Zakari, last Friday led a monitoring team to assess the impact of the incident.

    Although the rail tracks were not affected, the tremor was powerful enough to have created a huge gorge that shifted the protective wall, thus posing a potential threat to the tracks if not urgently addressed. The quake also exposed the pipeline that passed through the area.

    By the time Zakari’s team visited the site, the contractor, China Civil Engineering Construction Corporation (CCECC), had provided an engineering solution to cage the raging threat. A double-layered precast embankment was being constructed to check the threat, with the Permanent Secretary expressing satisfaction.

    “Our engineers and our supervising consultants have seen what the contractor has done and certified it okay. With this solution we are sure that the tremor has been put under check and would not be of any threat to this project whether now or in the near future,” Zakari said.

    He described the tremor as one of the unforeseen exigencies that occur on a project of such magnitude. He expressed satisfaction that the contractor has been able to provide a solution to protect the project and the rail line’s integrity.

    Zakari was, however, evasive when asked whether the development was capable of disrupting the planned take-off of commercial activity by October. He disclosed that the government was determined to ensure that it delivered a project that meets the best standard anywhere in the world.

    According to him, the contractor cannot be hastened to rail-road the project just because the government wants to meet its set deadline. “We have to choose between doing the job well and meeting our deadline.”

    The tremor, he said, was the least expected  the project. “I am sure that we never anticipated an earth tremor,” he said, adding that besides the tremor, the team visited to assess the impact of the proposed alteration to the Abeokuta train station.

    On the said station, he disclosed that though an elevator (lift) has been provided to be installed at the station, the contractor and government’s consultants are proposing an escalator instead to be constructed because of the anticipated passenger traffic. “We have therefore, come to see how this could be accommodated within the project,” he said.

    Mallam Alhassan disclosed that the corporation would rather deliver a project that meets global standards in safety precautions than to rush at delivering a project of doubtful integrity.

    “We  were shocked when we learnt that a tremor had occurred at a section of the project, and we are happy that the contractor is already providing an engineering solution that would arrest it,” Alhassan said, adding that all hands are on deck to ensure that the project meets the expectation of all.

    NRC Managing Director, Fidet Okhiria, however, assured that the incident may not affect the corporation’s plans to roll out commercial activity in October.

    Okhiria in an interview said: “With the two tracks now at kilometre 157, attention is back in Lagos, where we would want to ensure that we speed up the activity and link the speed train to Ebute Metta and from there to the Apapa Ports.”

    According to him, the contractor would be embarking on the construction of the tracks and the stations simultaneously, adding that “the construction company has assured that it would deliver on the three critical stations latest by December.”

    The two critical stations on the corridor, according to Okhiria, are Ebute Metta, Abeokuta and Ibadan. He added that the remaining seven minor ones would be delivered later.

    The express track gauge is designed to have 10 ultra-modern train stations, all of which have park and ride facilities. While four of these are in Lagos corridor; (Apapa, Ebute-Metta, Agege, Agbado), three are in Ogun State (Kajola, Papalanto, Abeokuta), and the remaining are in Oyo State (Olodo, Omi-Adio and Ibadan).

    The project lost much ground first to natural elements such as rains and the government’s inability to fully secure its right of way early. Almost the whole of last year was used to settle issues of right of way, especially in the Lagos corridor, forcing the contractor to shift attention to the forest between Lagos-Abeokuta and Abeokuta- Ibadan. This forced the contractor to deploy a four-gang segmentation method to execute the project.

    With the project reaching its last leg in Ibadan and the prospect of taking off getting clearer, the Federal Government is still struggling to compensate those whose properties were on the right of way, especially on the Lagos end.

    Due to its built up environment, establishing the right of way in Lagos, according to a top NRC source, was problematic. There were such as water main, gas and petroleum products pipelines, bridges (at Costain and Yaba) and hundreds of structures, from Iju to Apapa, including the Tejuosho International Market at Yaba.

    Also problematic was the relocation of affected public institutions such as the Nigerian Army Ordinance Corps at Alagomeji, Yaba, NRC Lagos District headquarters and staff quarters and a number of public institutions such installations as churches, mosques, firms and industrial concerns, forcing the committee to recommend that Lagos should be the last to be fixed.

    The project Manager Leo Yin, said the CCECC is determined to work round these challenges and deliver a project that would marvel Nigerians.

    Yin said: “The CCECC is determined to deliver world-class speed train system to Nigerians.”

    Though the stations might take longer, there is no doubt that a new narrative of Nigeria’s transportation architecture with the rail as its main artery would soon be here.

    Not only would this signal the emergence of new cities along the railway corridor, it also promises to have a massive effect on transportation patterns, especially in Lagos, where the 90 per cent of all containerised movements would be made by rail as well as 80 per cent of all liquid haulage.

    This will result in more sanity on the roads which are facing gradual lock-down due to the massive gridlocks in the city state.

    But more importantly is the opportunity for new housing stocks as more and more workers, traders and artisans may opt to live in contiguous states while still working in Lagos.

    With a speed train calibrated at 150 kilometres per hour, Ibadan to Lagos can then be achieved within an hour, while Abeokuta to Lagos can be done within 30 minutes. Nigerians are already upbeat about this huge possibility and are looking forward to it.

    One of such is Olatunji Michael, a business executive, who is already making preparations to mark his birthday in November on the speed train.

    “I have keenly followed the developments and happenings on the Lagos-Ibadan speed train and I was doubly happy when I learnt that commercial activity would be flagged off on the train in October. This made me to start planning to celebrate my birthday this year on the train. I will really love to take my family on the train ride to Ibadan and back. My wife and daughter are already planning of cutting my birthday cake with other travelers on board on the train, it would be much fun,” he said.

    Such possibilities as Michael’s are the immense opportunities that might be unlocked by the Lagos-Ibadan speed train.

  • Fed Govt sets February deadline for Lagos-Ibadan standard gauge

    •Amaechi insists passenger train to run by February
    •Minister: robbery attacks, molestation of contractors mar project

    The Federal Government yesterday set a new deadline for the completion of the Lagos-Ibadan standard gauge earlier scheduled to be delivered this month.

    At the monthly routine tour of the $1.7 billion project, Transportation minister Rotimi Amaechi said the project must be completed in February, adding that the passenger train must run on the standard gauge tracks same month.

    The Lagos-Ibadan standard gauge is a 156-kilometre project with 10 ultra-modern railway stations, bridges, tunnels and culverts.

    Speaking after the project’s work flow assessment meeting at Adumbu town, Papalanto in Ogun State, Amaechi said all hands were on deck to ensure that the trains run on the tracks at least from Lagos to Abeokuta, if not Ibadan, by February.

    “What we agreed on at this meeting is that by February, we must have a train service that makes transport sense. We would ensure that we have a situation where people can board our train from Lagos to Ibadan,” he said.

    To achieve this, the minister said the assessment meetings would henceforth be held twice a month, adding that the team would meet again on December 18 to assess the implementation of assignments.

    According to him, this pattern will continue until the project is delivered.

    Amaechi noted that though the elements posed a major challenge earlier in the year, the earthwork and civil engineering works were almost completed.

    He added: “We only have one or two bridges left in the entire project and I am very sure that by the time we are having our next meeting, this would have reduced to one, if at all there would still be any left…

    “I have just been informed by the contractor that they are facing serious security challenges from armed robbers, who steal their property. I have directed that they tackle that. This is what we have not been experiencing at the Abeokuta to Ibadan end of the project. This obviously also compounds the problem and slows down the pace of work,” he said.

    Amaechi said he directed that work be suspended on the stations to concentrate on the tracks because “we are convinced that once we achieve the tracks and begin to run trains on them, getting the stations in place would not be a problem”.

    He debunked insinuations that campaign activities may hamper the pace of work.

    The minister said his consenting to inspect the project on December 18, when the party would have kick-started its campaigns, showed the commitment of the government.

    “President Muhammadu Buhari is committed to building infrastructure. That is what we are also committed to actualising. Nothing will stop this project as we are committed to having a better Nigeria,” he added.

     

  • Amaechi admits failing health over Lagos-Ibadan standard gauge

    Amaechi admits failing health over Lagos-Ibadan standard gauge

    The Minister of Transportation, Mr Rotimi Amaechi, yesterday said the intense pressure of delivering the Lagos-Ibadan standard gauge is taking a toll on his health.

    Amaechi, who said he had never fallen ill, recalled that he was down two weeks ago due to pressure of trying to ensure the $1.5 billion project meets its December delivery deadline.

    The minister spoke at the site of China Civil Engineering Construction Company (CCECC) in Ibadan, the Oyo State capital, where he monitored sections Three and Four of the project.

    The sections lie between Ibadan and Abeokuta, the Ogun State capital.

    Amaechi said: “Nigerians should at least try and give credit to the Muhammadu Buhari administration for trying to deliver a three-year project within 19 months.”

    The minister noted that despite the seeming slow pace of the project, the Federal Government was determined to deliver it in December, but not later than next January.

    He added that the government would begin commercial services on the track by next January.

    Amaechi also said the Federal Government may have saved N2.8 billion in payment of compensation at the Ogun State segment of the project.

    He said: “At our last meeting in January, the contractor told us some part of M.K.O. Abiola Trade Fair Complex in Abeokuta and a housing estate comprising of 1,004 buildings, would gage to be demolished for the project. But after we reviewed the submission, we recommended that the contractor could shift to the right of the right of way where there are fewer encumbrances. If this advice is taken, we will be saving N2.8 billion in compensation. This is undoubtedly a huge sum that could have increased the cost of the project.”

    Amaechi said he would continue to engage with Governors Akinwunmi Ambode (Lagos) Ibikunle Amosun (Ogun) and Abiola Ajimobi (Oyo) to remove public facilities that may impede the speed of the project.

    The minister, who said work was not going on on all sections between section Three and Four (between Odeda and Abeokuta), warned the contractor against slowing down the pace of work.

    Those who accompanied the minister on the tour included the chairman of the Nigerian Railway Corporation (NRC), Usman Abubakar, directors of the Federal Ministry of Transportation, TEAM consultants and other stakeholders.

     

  • Lagos-Ibadan standard gauge will be ready 2018 – Amaechi

    Lagos-Ibadan standard gauge will be ready 2018 – Amaechi

    The Minister of Transportation, Rotimi Amaechi, said on Monday that the Lagos-Ibadan standard gauge rail gauge would be delivered by fourth quarter of 2018.

    The minister spoke during an assessment of the project at Ijoko, Ado Odo/Ota local government area of Ogun State.

    “We have said 2018 and that is a presidential directive. By December 2018, we want to see locomotives running from Lagos to Ibadan. We are committed to achieving this and the funds obtained from China Exim bank are already on ground to ensure that nothing obstructs this timeline.

    “Primary constraint the contractor identified are the height of two pedestrian bridges in Lagos (at Oshodi and Ikeja), and an ongoing flyover bridge at Ijoko, while the second problem was the multiplicity of level crossing on the rail’s right of way. The contractor said they could not proceed on laying the rail tracks until those impediments are sorted out.”

    Amaechi, who briefed journalists on site alongside the Ogun State Governor, Senator Ibikunle Amosun, said as soon as the issues of the flyover height and others associated with the right of way are addressed, actual construction work would commence on the standard gauge.

    He said while the project needs a minimum height of 6.5 metres, the identified bridges are about 4.5 metres high.

    The minister disclosed that the height of the bridge would have to be raised higher to accommodate future electrification of the train’s right of way.

    Amaechi and Governor Amosun agreed that engineers from the contractor and the state’s Ministry of Work and the Ministry of Transportation should meet and come up with the best way to resolve the logjam.

    He added: “As a ministry, we agree with the contractor for on-site meeting to ascertain the level of work on the project. Today we came to the conclusion that they have not commenced serious work and the reason why they have not commenced serious work is the problems they are having on the right of way.

    “So what I did today is to address those problems. One of the problems is the height of the flyovers and we are here to see the one which Ogun State is building.

    “We need to increase the current height from 4.8 to 6.5 metres because we may also want to ensure that there is electricity on the right of way because tomorrow we may start using electricity to power the train.

    “The engineers are going to meet from today and we will also meet by Wednesday. So by Friday, I would be meeting with Governor Amosun on the best option identified by the engineers and that’s what we’re going to take.”