Tag: national grid

  • Why national grid collapsed for second time in five days, by NISO

    Why national grid collapsed for second time in five days, by NISO

    Yesterday because a voltage disturbance originated from the Gombe Transmission Substation.

    There was a nationwide outage due to grid collapse earlier in the day.

    In an update, NISO described the incident as “partial system disturbance on the national grid”.

    NISO stated: “The Nigerian Independent System Operator (NISO) wishes to state that at approximately 10:48 hours on January 27, 2026, the national grid experienced a voltage disturbance which originated from the Gombe Transmission Substation.”

    NISO further stated that the voltage disturbance rapidly propagated across the network, affecting Jebba, Kainji, and subsequently Ayede Transmission Substations.

    Read Also: ‘Why national grid is collapsing repeatedly‘

    The incident, said the management, was accompanied by the tripping of some transmission lines and generating units, resulting in a partial system collapse.

    “Appropriate corrective actions were immediately implemented to stabilize the system and restore normal operations. Restoration, which began at about 11:11am has since been completed.

    “The incident only affected part of the grid therefore not a total collapse as reported by some media organizations,” NISO stated.

    NISO said the national grid has been fully restored and electricity supply across the affected areas has since returned to normal.

    With this occurrence, the NESI has recorded the second grid collapse in 2026 after recovering from its January 23rd experience.

  • Why national grid collapsed – NISO

    Why national grid collapsed – NISO

    The Nigerian Independent System Operator (NISO) said the grid collapsed at 10:48 hours on Tuesday because a voltage disturbance originated from the Gombe Transmission Substation.

    The Nation reported there was a nationwide outage due to grid collapse.

    But the management of NISO in a statement titled: “Update on partial system disturbance on the national grid,” explained: “The Nigerian Independent System Operator (NISO) wishes to state that at approximately 10:48 hours on January 27, 2026, the national grid experienced a voltage disturbance which originated from the Gombe Transmission Substation.”

    NISO further said the voltage disturbance rapidly propagated across the network, affecting Jebba, Kainji, and subsequently Ayede Transmission Substations. 

    The event, said the management, was accompanied by the tripping of some transmission lines and generating units, resulting in a partial system collapse.

    Read Also: Fubara never removed Tinubu’s portrait from Rivers Govt House, says Rivers govt

    The statement reads in part: “Appropriate corrective actions were immediately implemented to stabilise the system and restore normal operations. Restoration, which began at about 11:11am has since been completed.

    “The incident only affected part of the grid therefore not a total collapse as reported by some media organizations. Additional information can be obtained from our website: www.niso.org.ng.

    “The national grid has been fully restored and electricity supply across the affected areas has since returned to normal.”

    The Nigerian Electricity Supply Industry (NESI) was in a distress state whren generation dipped to 39MW  from only Delta (Gas) plant at 11:00 hours, when The Nation visited the website of the NISO.

    The system crashed from the 3,825MW recorded at 10:00 hours.

    According to its Electricity Distribution Profile, the NISO sent a total of 195MW to only three energy distributors at 11:59 hours.

    The load was allocated as follows: Benin DisCo 65MW, Ibadan DisCo 50MW and Kaduna DisCo 40MW. 

    Eight DisCos were in total blackout as the recorded 0MW allocation.

    With this occurrence, the NESI has recorded the second grid collapse in 2026 after recovering from its January 23 experience.

  • National grid collapses again, triggers nationwide blackout

    National grid collapses again, triggers nationwide blackout

    Nigeria’s electricity grid collapsed again on Tuesday morning, plunging the country into a widespread blackout in the second such incident within one week this year.

    As of 10:54 a.m., data published on the official website of the Nigerian Independent System Operator (NISO) showed that all major electricity Distribution Companies (DisCos) were receiving 0 megawatts of power, underscoring the scale of the disruption.

    Eko Electricity Distribution Company (EKEDC) confirmed the system collapse in a notice to customers, stating that the outage occurred at 10:48 a.m. and resulted in a loss of supply across its entire network.

    Read Also: ‘Why national grid is collapsing repeatedly‘

    The company said it is working closely with the Transmission Company of Nigeria (TCN) to restore the grid and assured customers that updates will be provided as restoration efforts progress.

    All major Distribution Companies across Nigeria—including Abuja, Benin, Eko, Enugu, Ibadan, Ikeja, Jos, Kaduna, Kano, Port Harcourt, and Yola—recorded zero megawatts (0 MW) of power supply, leaving total national generation at 0 MW.

    NISO has yet to issue an official statement on the latest collapse. 

    Stakeholders are worried that with the second incident coming barely five days after the first occurrence, represents the huge infrastructure strain and generation shortfalls bedeviling the country’s power sector.

  • ‘Why national grid is collapsing repeatedly‘

    ‘Why national grid is collapsing repeatedly‘

    • 60% of power plants unavailable
    • Report exposes Discos culpability

    The state of electricity supply in the country has become a source of concern for residents. After enjoying a relative supply for some parts of last year, especially in the second quarter, drawing applause from consumers, the euphoria that greeted this has gradually becoming worrisome.

    These concerns were more pronounced during the last yuletide, when several homes were left in the dark.  The situation, electricity Distribution Companies (DisCos) often explain, results  from national grid collapses, low power generation, gas supply shortages, or maintenance work by the Transmission Company of Nigeria (TCN). These issues, alongside infrastructure decay and vandalism, invariably leads to load shedding and intermittent supply. 

    Top officials of some Discos spoken to who pleaded for anonymity attributed power failures to a mix of upstream generation deficits, national grid instability and localised infrastructure challenges.

    For a long time, there has been several horse-trading associated across the value chain over erratic power supply. For instance, it is common for DisCos often cite “system-wide disturbances” or “grid collapses” from the National Control Centre (NCC) as the reason for total outages across their franchise areas. Besides, many outages are blamed on “gas limitations” at thermal power plants and a general drop in power generation. This is because when generation drops, the energy allocated to DisCos decreases, forcing them to implement load shedding.

    In situations like this, most hide under the guise of the feeder banding system. Under this framework, priority is given to “Band A” feeders, which are mandated to receive 20+ hours of supply thereby often leaving lower bands with significant outages when total available power is low.

    Yet, is the technical faults and maintenance of equipment, equipment vandalism like destruction of transformers and theft of cables; planned maintenance, like upgrading or repairing transmission lines, are also factor readily given as excuses by service providers.

    After enjoying relative stability in national grid in 2025, the facility experienced a first major collapse at the weekend caused by the simultaneous tripping of multiple 330kV transmission lines.

    With this incident coming early in the year, stakeholders are worried that it may not be a good omen for the sector notwithstanding the several assurances by government. In 2024, 12 grid collapses were recorded; 12 in 2025 and one already recorded this year.

    More worrisome is that the epileptic power supply has remained irrespective of the fiscal appropriation to the sector under the President Bola Tinubu administration.

    A cursory look at these allocation indicate that in the last three years, there has been a consistent increase in fiscal allocation to the Ministry of Power aimed at resolving the underlying issues that have consistently impeded growth in the sector, including the consistent grid collapses each year.

    A breakdown of the figures in the three years showed that the power ministry got a cumulative allocation of N239.5 billion in 2023; N344.097 billion in 2024; N2.1 trillion in the 2025 budget. The allocation in 2025 represented the government’s desire to make the sector work.

    A further breakdown of the figures show that the power sector recovery programme received N810 billion from the budget; special intervention project got N269.74 billion, while the presidential power initiative (PPI) transmission project received N150 billion, all in an attempt to tackle the enormous challenges in the nation’s power sector from specific and targeted approach.

    The Minister of Power, Adebayo Adelabu, assured that the ministry has set the agenda for Nigeria’s power sector in 2026, suggesting that the country has done enough to stabilise its grid in the previous year.

    But these challenges appear unresolved despite huge budgetary allocations to the power sector. Giving more insight into what may be the cause of the deep-seated challenges confronting the country’s electricity supply is a recent report by the Nigerian Electricity Regulatory Commission (NERC) for the third quarter of 2025. The report, released recently, indicated that over 60 per cent of power plants installed generation capacity in the country remained unavailable for transmission to the national grid in the third quarter of 2025.

    Read Also: NDPHC restores additional 450MW of generation capacity to national grid

    According to the NERC report, the average Plant Availability Factor (PAF) of all 28 grid-connected power plants stood at 39.86 per cent, meaning that 60.14 per cent of installed capacity could not be dispatched to the national grid at any point during the quarter. The figure represents only a 0.26 percentage-point increase from the 39.60 per cent recorded in Q2 2025, highlighting how limited progress has been in improving the operational readiness of generation assets.

    “In 2025/Q3, the average plant availability factor for all grid-connected plants was 39.86 per cent, that is, at any point in time during the quarter, 60.14 per cent of the installed capacity across the 28 grid-connected power plants was not available for dispatch onto the grid,” the report read.

    The PAF measures the ratio of a power plant’s declared available capacity to its manufacturer-rated installed capacity and is widely regarded by regulators as a key indicator of the health of the upstream segment of the Nigerian Electricity Supply Industry (NESI).

    It further noted that while 11 power plants recorded availability above 50 per cent, Ikeja Power Plant (Unit 1) emerged as the best-performing asset, posting a PAF of 99.24 per cent during the quarter. At the lower end, Sapele Steam Plant (Unit 1) recorded a PAF of just 2.66 per cent, while Alaoji Power Plant (Unit 1) failed to dispatch any electricity at all throughout the quarter.

    Significantly quarter-on-quarter improvements were recorded at Dadin-Kowa (+41.32pp), Zungeru (+33.29pp) and Okpai (+15.95pp), reflecting gains from improved hydrology and reduced outages.

    However, availability declined sharply at Ihovbor (Unit 2), which fell by 19.21 percentage points to 78.16 per cent, down from 97.38 per cent in Q2. Other plants that recorded notable drops included Geregu (Unit 1), Ibom Power, and Geregu (Unit 2).

    “Overall, 11 power plants had availability factors above 50 per cent, with Ikeja_1 power plant recording the highest availability factor at 99.24 per cent. On the other end of the spectrum, Sapele Steam_1 recorded a PAF of 2.66 per cent in 2025/Q3. Alaoji_1 power plant was not available to dispatch any energy onto the grid throughout the quarter.

     “Significant increases in PAF were recorded in Dadin-Kowa_1 (+41.32pp), Zungeru_1 (+33.29pp), and Okpai_1 (+15.95pp) power plants across the two quarters. Conversely, the PAF of Ihovbor_2 decreased significantly by 19.21pp during the quarter (78.16 per cent in 2025/Q3 compared to 97.38 per cent in 2025/Q2). Reductions in PAF were also recorded in Geregu_1 (- 12.79pp), Ibom power_1 (-10.34pp), and Geregu_2 (-8.41pp) power plants,” the NERC report said.

    The commission attributed the fluctuations in plant availability to mechanical outages, feedstock constraints, hydrological conditions and operational limitations, factors that have continued to undermine Nigeria’s generation capacity for over a decade.

    Beyond generation challenges, the report also highlighted weak energy offtake by electricity Discos, raising concerns over revenue recovery and market discipline. Under the Partial Activation of Contract regime, which came into force in July 2022, DisCos are required to off-take and pay for their Partially Contracted Capacity on a take-or-pay basis, even if they fail to utilise the power.

    In Q3 2025, average energy offtake by DisCos fell to 3,328.33 megawatt-hours per hour, representing a 7.10 per cent decline from 3,582.62MWh/h recorded in the preceding quarter.

    This decline occurred despite the fact that available contracted capacity dropped by only 2.43 per cent, suggesting that generation and transmission availability were sufficient to sustain previous offtake levels.

    Overall, cumulative DisCo energy offtake performance during the quarter stood at 87.39 per cent, down from 91.78 per cent in Q2, a 4.39 percentage-point decline.

     “All DisCos except Jos recorded a decline in their energy offtake performance during the quarter,” the report noted.

    The commission attributed the reduced offtake to a combination of infrastructure weaknesses, seasonal demand changes and commercial considerations.

    It noted that frequent network outages during the rainy season, driven by fragile distribution infrastructure, limited the ability of DisCos to evacuate power to customers.

    In addition, cooler weather conditions reduced domestic electricity demand, while some DisCos deliberately constrained supply to loss-prone feeders to minimise financial exposure.

    Under the Performance Monitoring Framework Orders issued in July 2024, DisCos are required to off-take at least 95 per cent of their available PCC or face regulatory sanctions.

    However, in Q3 2025, only Benin and Port Harcourt DisCos met the threshold, with offtake levels of 99.20 per cent and 95.65 per cent, respectively.

    The remaining nine DisCos, Abuja, Eko, Enugu, Ibadan, Ikeja, Jos, Kaduna, Kano and Yola, fell short, with Kaduna DisCo recording the lowest performance at 75.23 per cent.

     “The Commission has commenced the implementation of appropriate sanctions against defaulting DisCos,” the report stated.

    The figures reflect the persistent mismatch between installed capacity, available generation, and effective electricity delivery, a challenge that continues to frustrate households and businesses.

    Despite Nigeria’s installed generation capacity exceeding 13,000 megawatts, average operational availability and weak offtake mean that actual electricity delivered to consumers remains far below demand, reinforcing dependence on self-generation and driving up energy costs.

  • NISO restores national grid after nationwide blackout

    NISO restores national grid after nationwide blackout

    The Nigeria Independent System Operator (NISO) yesterday restored the national grid to 2,126 megawatts (Mw) total energy generation at 20:00 hour.

    It also raised the total energy sent to the 11 electricity Distribution Companies (DisCos) to 1,895Mw at 21:02 hours.

    There was a nationwide blackout as the Nigerian Electricity Supply Industry (NESI) recorded 0Mw total  energy generation at 16:00 hour.

    The grid developed issues that the NISO was yet to report its cause and restoration measures at press time, leading to the cut in the supply to the 11 electricity Distribution Companies (DisCos) from the average of 4,000MW on a normal day.

    The Nation however observed that the system dipped from 148.30MW at 15:00 hour, according to the NISO website dashboard.

    READ ALSO: Bridging the gaps in budget implementation

    On its distribution profile, the NISO revealed that total energy sent to the 11 electricity Distribution Companies (DisCos) at 16:46hour was 305MW.

    Meanwhile, the Eko Electric Distribution Company (EKEDC) in its power update notified its customers that there was loss of power supply throughout its network because there was a system collapse at 14:01 hour.

    According to the update, the energy distributor said it was working with its partners as it looked forward to a speedy restoration of the grid.

    The management said, “Dear Customers, Kindly be informed there was a system collapse at 14:01hour which has resulted in (sic) a loss of power supply across our network. We are currently working with our partners as we hope for the speedy restoration of the grid.”

    Similarly, the Abuja Electricity Distribution Company (AEDC) also informed its customers that there was a system disturbance on the national grid at 14:02pm today causing power outage across its franchise areas.

    It appealed to the customers that the company was coordinating with the relevant stakeholders to restore power fully as soon as the grid is stabilized.

    AEDC said, “Dear valued customers, we wish to inform you that a system disturbance occurred on the national grid at 14:02pm today causing power outage across our franchise areas.

    “Please be assured that we are coordinating closely with relevant stakeholders to restore power fully as soon as the grid is stabilized.”

  • JUST IN: National grid collapses to 0MW

    JUST IN: National grid collapses to 0MW

    • …disCos got 305MW, says NISO

    The Nigerian Electricity Supply Industry (NESI) on Monday recorded 0MW total energy generation at 16:00 hours.

    The system dipped from 148.30MW at 15:00 hours.

    The Nigerian Independent System Operator (NISO) disclosed this on its website.

    It revealed that total energy sent to the 11 electricity Distribution Companies (DisCos) at 16:46 hours was 305MW.

    Details shortly….

  • NDPHC restores additional 450MW of generation capacity to national grid

    NDPHC restores additional 450MW of generation capacity to national grid

    The Niger Delta Power Holding Company (NDPHC) has successfully restored additional 450 Megawatts (MW) of generation capacity to the national grid.

    Mr Emmanuel Ojor, Head, Corporate Communications and External Relations, NDPHC made this known in a statement in Abuja on Monday.

    According to him, the restoration of the additional megawatts followed the completion of scheduled maintenance on the Geregu NIPP plant in Ajaokuta, Kogi State.

    Ojor said that the four-week extended minor inspection, undertaken by Siemens Energy, was executed to enhance the facility’s operational reliability, performance, and efficiency, thereby extending the plant’s Equivalent Operating Hours (EOH) and operational life span.

    According to him, the Managing Director of NDPHC, Jennifer Adighije, confirmed that in the last one year the company had recovered six previously dormant gas turbines across its fleet of gas turbines.

    Adighije listed the turbines to include GT4 at the Calabar NIPP, GT1 at Omotosho II, GT1 and GT2 at Benin NIPP, GT4 at Sapele NIPP.

    “And currently GT3 and GT4 at Alaoji NIPP on standby for pre-commissioning after gas supply remedial works.

    “These restored units collectively would have cumulative 875MW additional capacity to NDPHC’s mechanical available generation; adding significant boost to national power generation capacity,” she said.

    Adighije also announced the commencement of restoration works on the 225MW Gbarain NIPP plant in Bayelsa State, which has been out of service since 2020.

    She described the restoration works as a major step toward recovering dormant national power in a bid to commercialise the output of the plant to serve critical commercial and industrial clusters within the Niger Delta region.

    “In spite of persistent sector-wide challenges, NDPHC has recorded several operational and financial milestones.

    “These include: Recovery of 110 containers with critical turbine parts and HRSG components, abandoned at Onne Port for over nine years.

    “Commencement of the Light Up Nigeria – Agbara industrial cluster project to connect the Agbara Industrial Estate to the grid and a 10MW embedded solar project for an industrial area in Kano.

    “Completion of key transmission and distribution projects in Borno and Delta States, as well as the completion of Afam–Ikot Ekpene 330kV double circuit transmission line,” she said.

    Adighije also listed other success stories of NDPHC to include recovery of over 10 million dollars in legacy debts from bilateral customers, securing 15 million dollars in insurance claims for the Alaoji plant fire incident.

    “Advanced engagements with  Nigerian Electricity Regulation  Commission (NERC)  on recovering NDPHC’s investments in TCN’s transmission expansion projects, resolution of longstanding commercial issues with ACCUGAS, leading to an amendment of gas supply agreement which reduces government’s exposure,” she said.

    Adighije  also said that to strengthen accountability and staff welfare, the management of NDPHC has introduced a procurement benchmarking desk for streamlining procurement practices, Computer-Based Testing (CBT) for enhanced staff performance management.

    She said that a management support allowance to cushion the impacts of fuel subsidy removal was also introduced.

    Adighije, however, reaffirmed NDPHC’s commitment to “restoring dormant capacity, stabilising operations, and supporting Nigeria’s goal of a more reliable and sustainable power supply value chain.

    She also that NDPHC’s management remains committed to transparency, accountability and constructive engagement with stakeholders in its quest for unlocking universal access to electricity for powering businesses and households across the country.

    (NAN)

  • Hope rekindles for ALSCON as FG moves to link company to national grid

    Hope rekindles for ALSCON as FG moves to link company to national grid

    The Aluminum Smelter Company of Nigeria (ALSCON) in Ikot Abasi, Akwa Ibom State may soon restart operations following the Federal Government’s moves to link the company to the national grid.

    The decision to resolve the challenge of uninterrupted power supply to the company, among other issues, were taken yesterday at meeting between the Minister of Power, Adebayo Adelabu and the management of ALSCON.

    The meeting, which at conference hall of ALSCON, also had representatives of the Transmission Company of Nigeria (TCN), the Niger Delta Power Holding Company in attendance.

    ALSCON management led by the Project manager Ruslan Matrenin and the Acting Managing Director, Engr. Ime Inyang had earlier in their presentations listed lack of gas and power, security and legal issues as some of the company ‘s challenges.

    Speaking with our correspondent after the meeting, Adelabu said that President Bola Tinubu was committed to the resuscitation of ALSCON which was established 27 years ago but shut down over a decade ago due to lack of power and gas supplies.

    The Minister said the FG would not allow the company to rot away because of its enormous economic potentials in the upstream, midstream and downstream sectors of Nigeria.

    He said: ” This investment like many others in the country has suffered from power problem in the past 27 years. It has not been connected to the national grid. And we are very much aware of the enormous potential of this company in the downstream, midstream and upstream conversion of aluminum.

    “It can create lots of employment for our teeming youths. It can also serve as supplier of raw materials for many downstream aluminum companies that can save us huge foreign exchange from import of these raw materials. 

    “Having appreciated this I have come to visit the company to to discuss with the managers and owners of the company and all the other stakeholders, the Transmission Company of Nigeria (TCN), Niger Delta Power Holding Company, and all the contractors involved to devise an immediate solution to the power problem this company has been facing.

    “And I am happy we have made very good progress with the meeting of today as we have determined a short time solution to the problem of power to solution to connect this company to the national grid and what the medium term solution is and we have made good progress”.

    He said that the company has the capacity of supply 540 megawatts of power to the national grid when linked to the 330kva substation which is being constructed by the Niger Delta Power Holding company.

    “But the most interesting part of this meeting is the fact  that the company also has the potential of supplying 540 megawatts of power to the national grid when fully activated. 

    “They have an installed capacity of 540 megawatts comprising of 6 turbines with 90 megawatts each and they all in very good condition. Once all the infrastructures are put in place and with the 330kva substation which is being constructed by the Niger Delta Power Holding Company together with the lines from Ikot Ekpene to Ikot Abasi they will be able to evacuate the entire of this 540 megawatts to the national grid. 

    “There is even the possibility of expanding this by 120 megawatts because this is an open circle. It can be made a combined mega circle by which the 120 megawatts transferred from the 120 powered turbines can be made to be 660 megawatts. 

    “You can imagine what this will add to the national grid. I have come today to listen to the company and other stakeholders and we have a solution in sight. All we need to do now is to go back and work on all the agreed action lines which I will personally supervise.

    “I believe that within the next ninety days we will be able to achieve the short term solution and the country will begin to feel the impact of this company beginning operations from the number of employment the company will generate in the country. 

    “They have the capacity to generate up to 3,000 employment and also supply of raw materials to downstream aluminum companies. This will save us millions of dollars and foreign exchange it will impact on our federal reserve and our gross domestic product, GDP. So it is a company that will add a lot to the economic prosperity of the country and the people of Nigeria.”.

    On gas supply , Alelabu said: “The company has a gas pipeline that has extended to the backyard which they have used in the past. But in the last 11 years they have not gotten gas supply even though they have a gas supply agreement.

     “This is all about commercials in gas supply. If the price is right the gas company will supply. It is a highly competitive market, preference will be given to those who pay higher. We believe they can sit down with the gas company and agree on a commercially viable price that will ensure that gas is supplied to the company.

    “I think that gas is the least of the problems here. The gas problem can be resolved with appropriate pricing. There is Ibom Power Company here that is getting gas which is less than 500 metres from here and the gas pipelines are working. It is a matter of agreeing on the right price with the gas company for the turbines to be powered immediately”.

  • National grid to get upgrade as govt approves new sub-stations

    National grid to get upgrade as govt approves new sub-stations

    Determined to tackle the incessant national grid collapse, the federal government has approved the construction of a two unit 60MVA, 132/33KV substation in Lalupon/Ejioku in Lagelu local government area of Oyo State.

    The project scope includes upgrades to the 60-year-old 330KV Ayede substation  and the construction of a new Asejire 330KV  substation, further stabilising the grid for over five million  residents.  Upon its completion, set at 24 months, the facility is expected to alleviate pressure on the national grid and improve energy supply.

    The substation, part of the Siemens-backed Presidential Power Initiative (PPI), is to be funded directly by the Federal Ministry of Power and aims to resolve frequent outages and grid instability plaguing the state capital.

    Similarly, the government also approved the rehabilitation and concessioning the decades-old Ikere Gorge Hydropower Plant and constructing a high-capacity new substation in Ibadan. The new substation to be located in Lalupon/Ejioku axis of Lagelu local government area will boost power supply to Iwo road, Monatan, Olodo and the adjoining areas in Ibadan.

    READ ALSO: Tribute to Omololu Olunloyo

    The projects, ratified during last Monday’s Federal Executive Council (FEC) meeting, include, will ensure that the Ikere Gorge Hydropower Plant, originally launched in 1979 under the military regime of former President Olusegun Obasanjo and operationalised in 1980 during President Shehu Shagari’s tenure, will now undergo a significant upgrade.

    In a statement signed by the Special Adviser, Strategic Communications and Media Relations to the Minister of Power, Bolaji Tunji, the project, which was initially stalled due to the preferred bidder’s failure to finalise terms, was re-concessioned to a reserve contractor, Messrs Quaint Power and Infrastructure Nigeria limited, after the original offer lapsed.

    The statement noted that the Power Minister Adebayo Adelabu, revealed that the facility’s capacity will expand from 6MW to 20MW under a 30-year public-private partnership (PPP) concession.

    Adelabu emphasised that upon its rehabilitation, the plant will prioritise energy access for the state’s Oke Ogun communities, with an upwardly revised concession fee ensuring long-term viability.

    Both initiatives, Adelabu noted, will serve as a backbone for strategic investments, enhance service delivery and align with President Bola Tinubu’s Renewed Hope Agenda for sustainable energy.

    They are expected to catalyse socio-economic growth by improving power reliability for households, small  businesses, industry, educational and health institutions.

    The minister underscored their role in resolving decades-old infrastructure gaps, stating: “These interventions will directly uplift livelihoods, attract industries, and position Oyo State as a model for Nigeria’s energy transition.”

    The approvals, the statement said, mark a critical milestone in federal government’s efforts to tackle grid vulnerabilities, which will have effects on national productivity.

  • National Grid: Govt sets terms for willing investors

    National Grid: Govt sets terms for willing investors

    The Federal Government is developing investment framework to channel private funding into the expansion and stabilization of the national grid, as part of efforts to ensure stable and adequate electricity supply.

    Minister of Power, Chief Adebayo Adelabu, in an exclusive interview yesterday, said that the government has started developing terms and guidelines that will serve as the framework for private sector’s participation in the transmission system.

    According to him, the framework is being built on a win-win model, allowing the government to secure ample funding for the national grid, while ensuring investors have opportunity to recover their investments and competitive returns.

    He said: “Some investors have indicated interest in building transmission lines, but we are working on putting a proper framework in place that would allow the private investor to recover cost. This is now the next step to create a framework that would allow private investors to recover costs on a commercial basis.

    “We have commissioned studies to invite private investors. So lastly, we are discussing establishing frameworks for private sector participation in investment in the national grid. The end of this year is here.

    “We have various offers from private investors. National grid is owned 100 per cent by government. But I can tell you, with other ministries competing for funds, we cannot fund the national grid alone.

    “It is an expanded national grid. If you look at the grid, it is too large, and there are some dedicated lines which some private investors have expressed interest”.

    Read Also: Easter: Don’t betray Nigeria like Judas lscariot – CAN to publc office holders

    Adelabu, in a statement by his Special Adviser on Strategic Communications and Media, Bolaji Tunji, also yesterday highlighted several milestones that have been recorded under the Presidential Power Initiative (PPI).

    He said several interventions by the President Bola Tinubu-led administration have helped to further galvanise the PPI project, known as Siemens deal.

    According to him, the Tinubu government has added fillip to the Siemens Power Project as an accelerated contract was signed to ensure visible progress in the project.

    He said: “The Presidential Power Initiative was conceived in August 2018, born from the strong bilateral relationship between Nigeria and Germany, with the goal of transforming Nigeria’s power sector by increasing generation, transmission, and distribution capacity. This administration, under the leadership of President Tinubu, has demonstrated an unwavering commitment to the PPI, recognizing its critical importance to opening up the economy and galvanising national development. 

    “To ensure the expeditious delivery of improved power supply to industrial clusters, households, and businesses, President Tinubu mandated the signing of an Acceleration Agreement. This commitment has translated into tangible results. Under the present administration, leadership, strengthened programme governance has expedited contract and financing approvals, leading to faster project implementation”.

    He outlined some of the milestones under the present administration apart from the execution of an Acceleration Agreement with Siemens Energy to fast-track the implementation of the PPI,  include the approval of  a new technical direction for the PPI, ensuring Siemens Energy focuses solely on upgrading and modernizing the transmission subsector through a Turnkey approach while the President also  approved that the distribution scope be delivered by other reputable Engineering Procurement and Construction (EPC) Companies with the requisite technical, financial, and financing capacity. 

    He pointed out that these strategic decisions were aimed at increasing grid capacity by an additional 4,000MW by the end of 2026, with an aspirational target of an additional 2,000MW, as directed by the Economic Management Team in 2024.

    Said he: ”Noteworthy is the fact that the implementation of the PPI commenced with the  installation and commissioning of 10 power transformers and 10 mobile substations across the country under the pilot phase of the PPI, which was manufactured and delivered in October 2023. In 2024, there was a focus on the implementation of the pilot project and the project initiation activities of the main phase of the PPI. 

    “Also under the administration, FGN Power Company implemented several transmission projects across the country, which have collectively increased the transmission wheeling capacity by over 700MW for industrial clusters, businesses, universities, and homes”.