Tag: Transmission Company of Nigeria (TCN)

  • Power supply dips to 2006mw

    …as transmission line trips North East to blackout

     

    The power supply from the Nigeria Electricity Supply Industry (NESI) at the weekend dropped to 83,570.30mwh (2006mw), according to the Independent System Operator (ISO) of the Transmission Company of Nigeria (TCN).

    Its operational report of Sunday showed that the industry recorded a peak generation of 4,452mw and lowest generation of 3,041mw on the previous day.

    The report also noted that “energy recorded on 22/09/2018 was 83,570.30MWH.” It however added that the generation at 06:00hour on Sunday was 3,340mw.

    The TCN however explained in a press statement that due to the tripping on fault of the Jos-Gombe 330kV Transmission Line, which had just undergone Annual Scheduled Maintenance, the North Eastern States including Bauchi, Gombe, Adamawa Borno, Yobe and Taraba are currently out of power supply.

    Its General Manager Public Affairs, Mrs. Ndidi Mbah, who issued the statement, noted that the line tripping occurred on 19:09 hour Saturday after it was re-energized.

    All efforts are being made by the company’s line engineering crew to resolve the problem and restore the transmission line accordingly.

    The statement added that the company took advantage of the outage to undertake the Annual Scheduled Maintenance of the 330kV transmission line from Jos to Gombe.

    Read Also: Power supply dips to 2006mw

    After the maintenance work has been completed by the combined engineering maintenance crew from Gombe and Jos Transmission Substations, the transmission line was re closed and energized at about 15:09 hours Saturday at 19:09 hours however, the line tripped due to fault on the line. TCN quickly initiated the patrol of the transmission line to detect and rectify the fault.

    The release noted that as at 18:30 pm, on Sunday the line engineering crew patrolling the Jos part of the 330kV transmission line has completed investigations on that part of the line, while the Gombe part of the transmission line trace is still ongoing. The entire line cannot be energized until both ends of the line trace have been concluded. Once completed, the findings would be analyzed and faults cleared, TCN will then re-energized the transmission line.

    Mbah said that the “TCN sincerely regrets inconveniences caused by the outage and also apologizes to the Government and people of the six North Eastern states affected by the outage, while assuring that efforts are ongoing to ensure a speedy completion of the transmission line trace and faults clearance in other to re close and energize the 330kV transmission line. Please bear with us.”

  • TCN raises capacity with 60MVA transformer in Edo, Ogun

    In line with the Buhari administration’s policy on incremental power, the Transmission Company of Nigeria (TCN) has again successfully completed the installation of two units of 60MVA 132/33kV power transformers at Papelanto and Okpella Transmission Substations in Ogun and Edo States respectively.

    The 60MVA transformer in Okpella will be commissioned by the Chairman of the Nigerian Electricity Regulatory Commission (NERC) on September 22, part of ceremony in his honour by his ancestral home, Igara Community in Edo State.

    Read Also:TCN’s capacity is 4,000mw not 7,000mw, say DisCos

    The 60MVA at Papalanto will be commissioned by the Minister of Power Works and Housing, Mr. Babatunde Raji Fashola SAN at a later date.

    The 60MVA power transformer installed at Okpella, is long overdue and will greatly support the industrial policy of His Excellency the Executive Governor of Edo State, Mr. Godwin Obaseki, which is based on the existence of huge deposit of limestone and other solid minerals in the area. Already BUA Cement has a factory at Okpella which could be expanded with improved power supply.

    According to the statement issued by TCN General Manager Public Affairs Mrs. Ndidi Mbah, prior to the new installation, the capacity of Okpella Substation was only 15MVA and has now increased to 75MVA with the installation of a 60MVA power transformer. Consequently, several communities including Okpella, BUA Cement Company, Aghenebode Town and environs, who are customers of Benin Electricity Distribution Company, are expected to experience improved power supply.

    Also, the capacity of Papalanto Substation was 75MVA before the new 60MVA power transformer was installed. The additional transformer has increased the stations capacity to 132MVA. Electricity users in Ilaro, Lapeleke, Sango, Onihale and environs in in Ogun State who are customers of Ibadan Electricity Distribution Company are expected to experience improved power supply. Potential eligible customers such as Lords Mint and Dolphin could also benefit from the increased supply.

    TCN noted that several projects are currently on-going in its network nationwide and re-affirmed its resolve to continue to pursue and implement the incremental power policy of the Federal Government by consistently investing in capacity expansion initiatives through its Transmission Rehabilitation and Expansion Program (TREP). TCN expressed gratitude to the Honourable Minister of Power Mr. Babatunde Raji Fashola for providing the needed leadership under which the company has continued to achieve laudable milestones.

  • TCN to DisCos: Copy stable network from Togo, Benin

    The Transmission Company of Nigeria (TCN) has asked Nigerians and the electricity distribution companies (DisCos) to take a cue of stable power network from the Republic of Benin and Togo that get 80% of their power supply from the Nigeria.

    Citing how a stable network should be, its Managing Director, Mohammed Gur Usman, said that “the reality is that we need investments in the DisCos. We need to change the distribution network. Some of you may not know. Any of you who has the opportunity of entering Republic of Benin, 80% of the electricity that is consumed in Benin and Togo is coming from Nigeria. ”

    Read Also:Fashola to DisCos: Deliver power or quit

    The Chief Executive Officer, who addressed reporters Monday night in Abuja, said “Go to Benin, you will have a stable power, but why is there no stable power in Nigeria?  Why is it that they have stable power and we don’t have, it is because our distribution network is weak. Go to Togo or just Benin here, and see how a distribution network is supposed to be.”

    He urged Nigerians to pray for investments in the DisCos for them to have stable power supply.

    He revealed that the TCN is working through its functional planning system with several DisCos to build their distribution models for them.

    According to him, the TCN redefined the issue of load rejection since April 2017 when it started referring to the situation as load unutilized.

    He explained that rejection presupposes deliberate intention not to take load but in some cases the unutilised load is not intentional.

    Continuing, he noted that “the DisCos have no capacity , investments have not entered the DisCos,” stressing that the at TCN has upgraded and boosted capacity in several cities such as Apo, Suleja, Keffi, Katampe, but “how many of the injection substations have the DisCos built”, he asked.

    Owing to lack of distribution injection substations, some of the distribution lines are connected directly to TCN transformers, an anomaly, which he claimed to have burnt two transformers in Abuja recently.

    The TCN boss said that “That is why we are begging to the government and whoever wishes to listen to us that investments need to enter the distribution companies…we are actually working with the government to see that the last mile which is now the weakest link in the power value chain, which is distribution, investments enter into that sector.”

    He noted that although the federal government had not shown interest in investing in the distribution, the Ministry of Power recently approved N72billion investment in the DisCos.

    He however noted that in order to improve power stability from the distribution value chain, the Federal Government has mandated the TCN to manage its N72billion investments in the DisCos.

    He noted that as at last week the company recovered 693 containers of transmission equipment out of 800 containers from the port with the support of President Muhammed Buhari and the  Minister of Power Works and Housing, Babatunde Fashola.

    His words: “We have been able to recover 693 containers out of the 800 containers that had been at the port. Some of them have been there for 15 years. Some of them have been auctioned. We have to follow the auctioneers to get it.”

    He disclosed that the TCN has secured €25million from the European Union for the implementation of projects.

    Usman revealed that because the TCN is underfunded the company made a case for extraordinary tariff review presented a case of tariff review to the Nigeria Electricity Regulatory Commission (NERC).

    The commission, he said, has responded that it would commission a regulatory asset consultant to review TCN asset for a cost reflective tariff.

    He noted that the TCN biggest problem is that of liquidity, which it is waiting for the government to also solve.

    The Managing Director disclosed that the company has commenced the procurement process for 300mw spinning reserves.

  • Edo monarchs at war over land

    There is a looming war between Uzairue and Auchi communities in Estako West local government area over alleged unprintable words used by the Otaru of Auchi, HRH Aliru Momoh, Ikelebe III on the state Deputy Governor, Hon Philip Shaibu.

    The lingering crisis between both communities was said to be over a parcel of land on which the Transmission Company of Nigeria (TCN) installed its sub-station.

    It was gathered that the TCN sub-stations could not be installed for over three years following ownership of the disputed land between‎ both communities until the intervention of the State Government.

    The Otaru of Auchi was said to have worked out on Hon Shaibu after using unsavoury utterances when he was at Auchi to represent Governor Godwin Obaseki to mark the Muslims celebration of Sallah last Friday.

    Read Also:Robbers kill musician in Edo

    Peeved by the abuse of one its prominent subjects, the Ogieneni of Uzairue, HRH Kadiri Imonikhe Omogbai IV, in a statement he personally signed warned that “the Uzairue will resist any attempt from the palace of the Otaru to rubbish, embarrass, hurt or tarnish the image of Shaibu”.

    The Ogieneni stated that the utterances of the Otaru of Auchi was aimed at embarrassing Shaibu.

    He said the friendly and accommodating nature must not be taken for granted by the Otaru of Auchi.

    The Ogieneni of Uzairue insisted that the land on which the TCN sub-station is cited belongs to the Uzairue saying it was unthinkable for any community, not even Auchi Kingdom to lay claim to the said land.

    He said the community released it because the State Government needed it for the good of the Etsako and the Afemai people in general.

    According to him, “In as much as we are very ready to live in peace with our neighbours, the Uzairue are not ready to yield an inch of their God-given land to any community not even Auchi.

    “We want to call on the state government and relevant security agencies to check the excesses of the Otaru of Auchi and his unguarded and overzealous palace Chiefs to avert the breakdown of law and order in the local government”.

    ‎In his reaction, the Otaru of Auchi, Aliru Momoh, Ikelebe III, said the Ogieneni “has right to do what he should do.

    “That right is given to man by God. I won’t join issues with him. I want to wait to see what Government will do”.

    The Otaru added that he has great love for his community and does not want any ‎of his subjects to die over land.

    “Government has the duty and responsibility to investigate. Government cannot judge without looking at the evidence. If Government does that that would be injustice,” the Otaru said.

  • TCN urges DisCos to recapitalize 

    …fears imminent system collapse over load rejection

     

    Owing to the volume of idle power waiting for evacuation, the Transmission Company of Nigeria ((TCN), Wednesday called on the electricity Distribution Companies (DisCos) to recapitalize the investment in order to boost their capacity.

    The company expressed fears that despite its existing capacity, load rejection from the DisCos, which causes high frequency and system collapse could still persist unless the distribution companies are ready to distribute their loads.

    The Assistant General Manager, Operation, Engr. Smart Omo Omoragbon made this call during a media tour all the Ikeja West, Transmission sub-station, Ipaja-Ayobo, Lagos.

    He noted that as the government provides funding to the transmission expansion that has resulted in a strengthened transmission capacity, the private investors of the distribution sub-chain should recapitalize to be able to distribute their load allocation.

    His words: “They are also improving but it might not also be at the same pace because the federal government is providing our funds. Their problem as far as fund is concern, they also need to recapitalize. Their network needs to be upgraded so that they can deliver energy to the Nigerian people.”

    Technically, transmission capacity is expected to be double of transmission capacity, but in the Nigeria Electricity Supply Industry, distribution capacity is a far cry from the transmission capacity of about 7,000Mega Watts (MW).

    While at Ejigbo 132/33KV substation, the capacity is presently 250MVA by the time the 100MVA is commissioned the capacity would have increased to 300MVA. Besides, a mobile transformer is presently bridging the gap when the need arises; it was learnt from the Assistant General Manager, Akintola Mojeed.

    He said the TCN was interfacing with the DisCos on how to catch up with the transmission expansion by radiating another feeder in Igando and Ijegun to separate the two locations.

    Speaking with journalists at the Ejigbo sub-station, the Deputy Director of Press, Etore Thomas said that “we are transmitting more and generating less.”

    She however added that the distribution companies were doing the “needful but they should step up their capacities.”

    The team was also at Akamgba sub-station, where the Assistant General Manager of Transmission, Engr. Anthony Dim, said there was consistent increase in the capacity, stressing that for the past two years “we have experienced capacity increase in virtually all the sub-stations.”

    Within the period, according to him, two MVAs have been added with 300MvA on the site, which would be completed before the year ends.

    Continuing, he revealed that the station has an idle load that it “was waiting to be picked up by Eko Distribution Company.

    “We are trying to ask them to come here because we have more than enough capacity,” stressing that “Eko must evacuate the load; by the time they are not evacuating we will be reducing generation. For instance, if the generation is high, it can also lead to system collapse.

    “And that is why we cannot guarantee that system collapse is now history. It is a function of the load that is in the system. If the the load in the system is not evacuated the frequency will be extraordinarily high and it can lead to system collapse.

    “With the addition of the 2/60MVA transformer, we are set to increase the capacity. So we have so much load here that we are waiting for the DisCo to tap into from this station.”

    Read Also: TCN inaugurates 100MVA transformer, assures increase in power supply

  • TCN inaugurates 100MVA transformer, assures increase in power supply

    The management of Transmission Company of Nigeria ( TCN ), on Monday inaugurated 100 MVA transformer at Alimosho substation, Lagos to boost electricity supply to residents within Ikeja Disco.

    Mr Usman Mohammed, the Managing Director of TCN, while inaugurating the project, said the company was not just concerned in increasing the quantum of power, but also the quality of electricity being supplied.

    Mohammed said that the upgrading of 1X30MVA with 1x100MVA transformer at Alimosho 132/33KV transmission substation had raised the station output capacity from 160 MVA to 230 MVA.

    “With this development, TCN has not only established adequate Transformer capacity to serve these parts of Lagos but has also provided the necessary redundancy in line with the requirements of N-1 reliability criterion at Alimosho transmission substations at present.

    “In addition, two projects under the transmission rehabilitation and expansion programme will intervene in Lagos and environs.

    “The Nigeria Electricity Transmission Access Project ( NETAP ) will significantly upgrade the following substations; Ijora, Lekki, Alagbon, Alausa, Maryland, Otta, Egbin, Omowu odofun, Itire and Akoka.

    “Similarly, the preparation for the Lagos Ogun Transmission Project financed by JICA has reached advanced stage.

    “The project will build transmission lines and substations in Likosi, Arigbajo, Badagry, New Agbara, Mountain of Fire and Redeem among others,’’ he said.

    According to Mohammed, all the projects that TCN is implementing in Lagos and Ogun are consistent with both states policies on power development.

    He said that TCN would appreciate the support of the two states in resolving disputes over land where substations had been built.

    Mohammed said that the ongoing project was part of the World Bank 300 million dollars on International Development Association credit to support the rehabilitation and upgrade of Nigeria’s electricity transmission substations and lines.

    He said that the project was part of the Federal Government’s power sector recovery programme to boost electricity generation and distribution system.

    The managing director noted that the Nigeria Electricity Transmission Project would help to address key bottlenecks in the transmission network and improve access to affordable and reliable electricity service to Nigerians.

    The TCN boss said that the company had secured close to two billion dollars for the rehabilitation of National Grid infrastructure and expansion of its transmission capacities up to 20,000 megawatts target within the next three years.

    He, however, lauded Mr Babatunde Fashola, the Minister of Power, Works and Housing under whose leadership, TCN was transformed from the weakest to the strongest in the NEI value chain.

    “I wish to use this occasion to call on the distribution companies to invest in their network so that the massive investment by TCN and generation companies can lead to economic growth and development of Nigeria.’’

    According to him, with the replacement of 1X30MVA with 1X100MVA, 132/33kV transformers at Alimosho 132/33KV substation, the communities under the network of Ikeja DISCO are expected to experience remarkable improvement in power supply.

    “This would increase supply to Gowon and Shagari Estates, New Ipaja, Ayobo, Abule Egba, Ekoro, Ajasa Command, Okunola, Idimu Road, Olorun Adaba, Shasha, Sanyos Layout, Akowonjo, Orile-Agege, Arigbanla, Dopemu, Tower Alumium, Oko Oba and Oki areas.’’

    NAN

  • TCN commissions 60MVAR capacitor bank to improve electricity voltage in FCT

    The Transmission Company of Nigeria ( TCN ), has commissioned a 60MVAR Capacitor Bank at the Apo 132/33Kv substation to improve quality and voltage of electricity supply to consumers in the Federal Capital Territory ( FCT ).

    The Minster of Power, Works and Housing, Mr Babatunde Fashola, said at the commissioning of the project on Thursday that it would improve quality of power in terms of voltage to some communities in the FCT.

    He listed the communities to include Apo, Guzape, Garki, Lugbe, Asokoro, and some parts of Central Area.

    Fashola said the provision of the facility was part of the implementation of incremental power programme of the Federal Government.

    “We are here because we promised incremental power, we have improved the quantity that is available. We have improved the quantity of power that is being transported.

    “We have improved the quantity of power that is being distributed, but our work is not finished.

    “It is one thing to have power, it is another thing for the quality of the power to be good and today we came to address the quality of power.

    “Our population has grown over the last 20 years without a commensurate expansion in the services that we have installed, and that is partly why you experience issues like low voltage, load shedding and other issues.

    “Today, we added a capacitor bank here which will help to increase and improve the quality of power by improving the voltage.

    “Voltage is critical not only to general safety but also to quality of life and cost,’’ the minister said.

    The installation of the power capacitor bank was necessitated by the on-going transmission rehabilitation and reinforcement of power infrastructure to improve wheeling capacity at the interface level with DisCos.

    The installation of the facility was done by the Japanese International Cooperation Agency ( JICA ) through mutual cooperation between the Nigerian and Japanese governments to improve electricity supply to Abuja, Nasarawa and Benue States.

    The contract for the project was awarded to EPC contractor in July 2016 at the cost of 12.1 million dollars.

    Fashola said the Japanese government through JICA was one of the partners driving the change promised Nigerians by President Muhammadu Buhari.

    “This project is part of the change for a better Nigeria, the president need partners and one of the partners is the Japanese government represented in Nigeria by JAICA,” Fashola explained.

    Earlier, the Managing Director of TCN, Mr Mohammed Gur-Usman, said the project was one of many the company had undertaken under the collaboration component of the incremental power project.

    He said the Apo sub-station capacitor bank was done jointly with another capacitor bank in Keffi, adding that the Keffi component had 25MVAR as capacity value, while Apo has 60MVAR.

    Gur-Usman said under the collaboration, JICA would support the upgrade of the Apapa sub-station from 90MW to 160MW and rehabilitation of Akangba sub-station

    He said negotiations were on-going with JICA to also rehabilitate Isolo, Ojo and Ikeja West subs-stations.

    “JICA is supporting us with a loan that will help us increase transmission capacity between Lagos and Ogun States to more than 1,000MW,” Gur-Usman said.

    The Chief Representative of JICA at the Nigerian Office, Mr Katsutoshi Komori, said JICA was working in the areas of infrastructure development in Nigeria.

    He said improving infrastructure like power was one of the priority areas of JICA programmes to enhance Nigeria’s potential economic growth.

    He explained that the provision of the capacitor was to mitigate the suffering of consumers from voltage loss and load shedding due to increasing population and distance from power infrastructure.

    According to him, the project will help stabilise power supply in the region to approximately 7,000 households.

    NAN

  • FG upgrades electricity distribution capacity in Umuahia, Aba

    Mr Babatunde Fashola, Minister for Power, Works and Housing, said the electricity transmission capacities of Umuahia and Aba transmission sub-stations have been upgraded to boost power supply in Abia and environs.

    Speaking at the inauguration of the 40MVA 132/33KVA mobile power transformer at Umuahia transmission sub-station on Monday, Fashola said the move was part of the Federal Government’s commitment to boosting the socio-economic growth of the country.

    He said the growing population and consequent demand for more power supply made it pertinent to increase the volume of power supplied through the sub-stations in Abia.

    Fashola noted that increasing the capacity of Umuahia sub-station would improve electricity supply to Umuahia metropolis and its environs as well as some parts of Imo.

    “It is no longer news that our power generation has risen to 7000 MW but the distribution capacity still lags 2000 MW behind. That means we need to expand distribution and transmission support system,” he said.

    The minister said the new mobile power transformer installed by the Transmission Company of Nigeria ( TCN ) would increase the capacity of the Umuahia transmission sub-station from 80MVA to 120MVA.

    According to him, the commissioning of the 60MVA 132/33KVA power transformer in Aba transmission sub-station would also increase the sub-station’s capacity from 147.5MVA to 227.5MVA.

    Fashiola said he was in Abia to discover, first hand, the local problems encountered in power supply and to develop solutions.

    “Our purpose is to hold the annual monthly meeting with stakeholders to deepen our service to Nigerians with respect to accessing adequate power supply.

    “It is also to familiarise ourselves with the power installations and assets that generate, transmit and distribute power in the state,” he said.

    In his remarks, Gov. Okezie Ikpeazu of Abia commended the Federal Government for boosting power supply in Abia.

    Ikpeazu said that the actualisation of the socioeconomic development of the state and nation at large required a well structured power distribution system.

    NAN

  • House Committee promises adequate funding for TCN projects

    The House of Representatives Committee on privatisation has assured that it will make adequate budgetary provision to complete all on-going Transmission Company of Nigeria ( TCN ) power projects in the country.

    The Chairman of the committee, Hon. Ahmed Yerima, gave the assurance when he led members to an over-sight function and interaction with management of Enugu Electricity Distribution Company ( EEDC ) on Monday in Enugu.

    Yerima noted that the on-going TCN power projects were critical to the social and economic growth of the country.

    “We are looking for a way to meet all the TCN budgetary needs for the completion of their numerous on-going projects at various degrees of completion to ensure stable power supply in the country.

    “These projects are critical to the economic and social growth of the country.

    “When completed and put to use, it will translate to more jobs, employments, profits, more money, security and general well-being of our people in the country,” he said.

    The chairman also said the committee would consider an all-encompassing legislature that would checkmate energy theft in the country.

    “It is basically a moral issue for people not to do the right thing like paying for electricity they had consumed.

    “We have decided to look at the issue of energy theft from a broader view. We will see what we can do on it,” he said.

    Yerima said the committee had fruitful deliberations with the management of EEDC, especially on issues hindering the progress of the company and service delivery to the people.

    “It was a fruitful session with the EEDC management, as we came purposefully to see, hear, interact and find a common ground to improve power supply for the good of Nigerians.

    “It is a known fact that the power sector is the key driver of the economy as well as other socio-political necessities meant to better the lives of Nigerians,’’ he added.

    Earlier, the Acting Managing Director of EEDC, Mr Paul Okeke said the company had improved its operations, using smart meters, customer service, ease of payment and reduced time of repairs of faulty installations.

    Okeke said in spite of the achievements, there were so many challenges facing the company, adding that energy theft was one of its major problems.

    “I will implore the lawmakers to enact a law that will put stringent penalty on people that engage in energy theft.

    “In the same vein, I would like the committee to come up with legislation to establish a special court for prosecution of those who engage in energy theft,’’ he appealed.

    The committee also inspected EEDC’s smart meter assembling section and smart meter monitoring network room.

    NAN

  • FG alleges GenCos plans to disrupt power supply for politics

    The Minister of Power Works and Housing, Babatunde Fashola Monday  revealed that he received reports on plans emanating from some secret meetings of some electricity Generation Companies (GenCos) to disrupt power supply because of political gains.

    His words: “Let me say it very clearly to some of these people that I get reports on some of the clandestine meetings they hold with the view to disrupt power supply for political capital.”

    He dropped the hint that the power firms have dragged the federal government to court over its regulation, stressing that the suit coming at the time that there is increase in power supply is an indication of the intention of the plaintiff to blackmail the government and hold the citizenry hostage.

    He wondered “whether the period when this sector is now making progress does not suggest an intention to blackmail government and to hold the citizens hostage?”

    The former Lagos state government, who is also a Senior Advocate of Nigeria vowed to defend government’s position in the law court, where he has lived all his life.

    He made the disclosure at the 25th Monthly Power Sector meeting in Uyo, Akwa Ibom State capital.

    The power firms had sued the Federal Government for discriminatory treatment against them and the gas suppliers. They claimed that the government’s was scheming to give Azura Power West Africa Limited and Accugas Limited to disadvantage of the entire power sector.

    The representatives of the GenCos in the suit at the Federal High Court, Abuja, are Mainstream Energy Solutions Limited, Transcorp Power Limited, Egbin Power Plc, and Northsouth Power Limited.

    Fashola however noted that only the power firms tabled their complaints to the ministry and dragged the government to the court only a week after that was not sufficient for the government to look into their grievances and react.

    He urged them to be fair in good conscience to the court of law and court of public opinion about the rival firms that they complained of. The minister submitted that the other new company has a partial risk guarantee in its contract which the plaintiffs do not process.

    Fashola tasked the plaintiff to be ready to tell the citizens how they felt first when others groups went to court to stop the implementation of tariffs approved by NERC.

    He said “I was their supporter then asking Nigerians to bear with the tariff. You must explain to the court of public opinion whether they went to court before this government approved for them the N701billion payment assurance guarantee which enables to to receive payment on their monthly power bills.

    “When they are in that court, they must also tell the court that they are indebted to gas companies and to their banks because they were receiving less than 50% of their bills. And in doing so, they must tell the court that they now receive 80% of their bills from less than 50% because the Buhari’s government intervened with the assurance guarantee.

    “They must also tell the court when they get there or while they are there that unlike before when they were paid in Naira, from money that was received from international customers, we sell power to Niger Republic, Chad, Niger and Togo, under an international arrangement. They must tell the court that they are now receiving payments in dollars instead of in the Naira, which used to be the case.

    “They must also tell the court when they get their and also tell the court of public opinion that that there is a new GenCos  getting paid 100% while they are getting 80%. And they must explain to the court that the reason is that that new GenCos has a partial risk guarantee in its contract and they do not. They was the contract they signed.”

    But the unsaid in and the Genesis of the veneer of hatred in the sector was the introduction of the mini-grid regulation that the Nigerian Electricity Regulatory Commission presented to the ministry last year making legal ways for competitive participation in power generation instead of the monopoly -like system that held the sector down for years.

    Yesterday however, Fashola recalled that the of privatization of the sector was not meant to displace the hold monopoly of government with a new monopoly of private businessmen.

    He added that there was already progress emanating from the implementation of the regulation p, adding that “So if those people bother to look around them and they look at roof tops across Nigeria, you will see increased number of solar panel.

    “And the Nigerian Mini Grid Regulation we have issued encouraged this to happen more and more and it will not stop. So for those who want to produce solar one megawatt and below we now have a regulation that allows.”

    Fashola presented the Meter Asset Provider 2018 Regulation to the State Governor, Emmanuel Udom, making Akwa Ibom the first state to receive a copy of the regulation of the Nigeria Electricity Regulatory Commission (NERC).

    He recalled that the government pursued an out of court judgement in a case that lasted from 2013 to 2017 to get N39billion from a liability of N119billion.

    He said that negotiations were still ongoing for fundings for rural electrification, mini-grid and DisCos distribution expansion financing that government hopes to complete before the end of the year.

    According to him, the Transmission Company of Nigeria (TCN) has continued its wheeling capacity, upgrade of its substations in partnership with the Niger Delta Power Holding Company.

    He reported to the stakeholders at the meeting that the Calabar substation has been completed and ready to be energized: Uyo substation is already completed and ready  to be energized in a matter of days. He said that substations in Karu, Nassarawa, Abeokuta among others have been completed and now in service.

    Fashola said it was no longer news that the sector has reached a 7,000mw generation capacity and now has 5000mw distribution capacity.

    He broke the news that in the last month the ministry met with the Manufacturers Association of Nigeria, DiscOs and GenCos and TCN on how to implement the eligible customer policy and increase connectivity to the 2,000mw now available.

    He said that the meeting was productive and “report reaching me is that is what is outstanding is agreement on the tariff that will be paid on the eligible customer.”

    Speaking the NERC commissioner, Dafe Agenife, who presented the Meter Asset Provider 2018 Regulation to the minister, said that issues of availability of metering and estimated billings were recurring where the commission went to.

    He said that the commission had consultations with different stakeholders, agency and consumers on the regulation.

    He submitted that the findings was that NERC could not leave the task to the DisCos alone as other investors must come on stream, hence the Meter Asset Provider Regulation.

    The commissioner Before you today is the NERC Meter Asset Provider 2018,” adding that four years after privatization customers are still complaining which necessitated the regulation to have independent people approved by NERC and contracted by the DisCos  to bridge the metering gap.

    In bridging the gap, he said, customers will now have the option of self-financing, obtains meters from the asset providers to pay the metering service charge for a period of 10 years.

    The meter asset providers will also ensure that the meters are maintained 48hours should anything goes wrong with the meters, he added.

    According to him, it is estimated to produce an investment of over N200billion in the next three years in the industry.

    The regulation, he said would create jobs owing to its 30% local content initiative.

    Read Also: How Fed Govt is resolving power supply problem