Tag: TCN

  • Vandals destroy six power transmission towers of TCN in Delta

    The Transmission Company of Nigeria (TCN) says six of its power transmission towers along Delta-Benin and Delta–Sapele-Benin 330kV transmission line routes have been vandalised with some of the towers removed.

    Ndidi Mbah, TCN’s General Manager, Public Affairs in a statement on Monday in Abuja said the vandalism, coupled with the heavy rainfall of March 17, caused the collapse of tower No 61 alone.

    Mbah said when the transmission line tripped, a patrol team was dispatched to investigate the cause and investigations revealed that the tower had collapsed and its aluminum conductors were on the ground.

    She said the patrol team also discovered that tower members of five other towers including the tower directly opposite tower 61 on the Ughelli – Benin line route were missing.

    According to her, the Delta-Benin and Delta-Sapele-Benin 330kV transmission lines evacuate power from Transcorp power Limited, in Ughelli into the national grid.

    “With the collapse of tower No 61 on Delta-Benin line, TCN is now evacuating the power through Delta – Sapele- Benin 330kV transmission line alone.

    “Although the collapsed tower has not affected power evacuation, transmission lines redundancy is effected until the second line is restored,’’she said.

    She said TCN had been facing the challenge of repeated attacks by vandals on the Benin transmission line axis since December 2018.

    Mbah said the company had also made formal reports to security operatives and to the traditional rulers in the area, including the King of Okpe Land and the Ovie of Oghara.

    Read also: TCN groans as capacity utilisation dips to 14.8 per cent

    According to her, the traditional leaders equally held meetings with their subjects to address the menace of vandalism in the axis,  but to no avail.

    She, however, said TCN had already mobilised its quick response and repair engineering team to the site, noting that repair works on the affected towers would be completed in four weeks.

    “TCN reiterates the need for host communities to watch over electricity installations in their domain, to forestall the destructive activities of vandals,’’ she said.

    She also urged electricity customers nationwide to report any unusual activities around electrical installations to appropriate authorities (NAN)

  • TCN groans as capacity utilisation dips to 14.8 per cent

    The Transmission Company of Nigeria (TCN) has raised concern as the distributor Company of its Odogun Yan substation located in Ikorodu, Lagos State has reduced its load utilization to 14.8 per cent.

    Lamenting about the disappointment, which he described as a waste of investment, the Assistant General Manager, Transmission Egbin Sub-region, Ajiboye Oluwagbenga who conducted the Federal Ministry of Power inspection team from Abuja, explained that although the 132/33KVA substation has 96mw load allocation, it is currently grossly under-utilized.

    He said there was very high hope for demand for the load when the TCN was constructing the plant but the Ikeja Electric which is the major distributor of the power is now rejecting the load and rendering the plant almost idle.

    His words: “It is a 2*60MVA. It was commissioned by the minister 7th of May 2018. Presently our projection about the loading is not being met. We have 2*60MVA which is equivalent to 96MW. But currently we are just making about 14MW. This morning it was on 20Mw but now it is on 14MW, translating to about 14.8% loading.”

    The major target of the power consumer which is Mega Steel was utilizing 28MW upon the commissioning of the project last year, but he noted that the dwindling economy has compelled the firm to reduce its demand for power.

    According to him, prior to the completion of the Odogun Yan project, the TCN was only wheeling power from a 132KV single line between Ikorodu and Sagamu. We call it 132KV single line.

    Speaking earlier, at the Ikorodu substation, he added that “With the connection of Ikorodu-Sagamu to double circuit, there is a need for additional bay at Ikorodu since it is going to be additional line now. We need to have the second bay. It is the one that is being constructed by these people.”

    According to him, “the bay which is the expansion project is almost 95%. Every equipment has been tested. This one will take just one day to fix this thing back. It was with Odogun Yan project and it was awarded in 2010. And it commencement was 2011-2012 while completion and commissioning was in May 2018. The line will be completed in July this year. It is a different project.”

    At the Odogun Yan substation, the Principal Manager, System Operation Area Control, Mr. Adeniyi Adeleke called on the Federal Government to draft armed security personnel from the Nigerian Police Force and the Nigerian Security and Civil Defence Corps to take over the surveillance of the power plant.

    He revealed to the inspection team that was on a fact-finding mission that there are no Closed Circuit Television (CCTV) in the substation.

    He said that “We don’t have issues with the community presently but the security situation is not okay. We will appreciate a situation where we can have law enforcement agents being here 24/7 guarding the station, equipment and the personnel. We will really appreciate that. We don’t have CCT in this station. Robbers had entered here and we didn’t know where they came in from.

    “During construction, this place is very volatile. On two occasions we were robbed here. We brought full load iron rods, immediately we off-loaded them, the robbers came to cart them away despite the police and OPC that were here. We had to order for other rods.

    “When we come here at night even 7:00pm you cannot pass here. Staff are being scheduled to resume at the time that is comfortable for them.

    We need armed security men to guard this station. Safety of the personnel is the most important thing before we talk of the equipment.”

    Another major challenge that the personnel pointed out was that of shortage of manpower and lack of operating vehicles in the substation.

    Continuing, he recalled that “on Sunday We are supposed to have five staff but we have only three. We are just managing and people find it difficult to go on leave. Imagine only two people running this substation, which operates every day.

    “They are three in the station and somebody must have some rest.

    We need more hands. We need training programmes for our staff. We don’t even have official vehicles to run the station.”

  • TCN wheels 4,613.5mw daily energy peak to GenCos

    The Transmission Company of Nigeria (TCN) on Saturday announced that power sector has achieved a new daily grid energy peak of 110,724.93MWH (4,613.5mw) on Wednesday.

    This is an improvement on the previous maximum daily grid energy peak of 109,372,01MWH (4,557.1mw) attained over two years ago on the 2nd of February 2016.

    In a statement by the General Manager (Public Affairs), Ndidi Mbah, TCN said that the new maximum daily energy peak is much higher than the last one attained over two years ago by 1,352.92MWH.

    TCN explained the maximum daily grid energy of 110,724.93MWH is different from the peak grid generation (power) of 5,375.0MW attained on February 7, 2019.

    The maximum daily grid energy refers to the quantum of energy that is wheeled from generators to distribution load centers nationwide throughout a whole day (00.00Hrs 24:00Hrs).

    This is measured in Maga Watts Hour, while the peak grid generation (power), which is a singular reading or high point in grid generation, is measured in Megawatts.

    According to the statement, the new maximum daily energy and the peak generation (power) show TC has enhanced capacity and capability to wheel and transmit more power, over time, into the grid, provided the Distribution companies are ready to serve the load to electricity consumers.

    It is also evidence the ongoing Transmission Rehabilitation and Expansion Program (TREP) being executed by TCN is paying off.

    TCN noted that the success of TREP is in line with this administration’s incremental power policy and that it is poised to continue to play its role in the power sector value chain as well as ensure that its grid expansion plan is implemented on time.

    Implementation of TREP, it said, is tied to its 20 Year Least Cost Transmission Expansion Master Plan, aimed at systematically expanding the nation’s transmission grid.

  • FG stops payment of GenCos shortfall

    …urges evacuation of stranded 2,000mw for revenue

     

    The Federal Government on Tuesday announced its exit from the payment of the shortfall for the 4000mega watts per hour (mwh) to the Electricity Generation Companies (GenCos).

    According to the Permanent Secretary, Ministry of Power, Dr. Louis Edozein, who broke the news to stakeholders at the Nigerian Electricity Regulatory Commission (NERC) workshop on Eligible Customer Regulation in Abuja, the Electric Power Sector Act does not make provision for the Nigerian Bulk Electricity Trading Company (NBET) to pay for the shortfall to the GenCos.

    He told the stakeholders that in line with the contractual agreements, it is the consumers, who should pay for the power they consume.

    His words: “In addition to that 2,000 MW, the 4,000mwh that is consistently being delivered is not fully paid for. Government through the nation’s insurance Programme is paying the generation companies for any shortfall payment from NBET.

    “Clearly that is not what act intends the industry to be. And ultimately government has to exit from this role.

    “So, it is this regulation that will ensure that not just stranded power but delivered power, is delivered to consumers who are contractually bound to pay for it. And if they do not pay for it they do not enjoy the service.”

    The Permanent Secretary noted that it is obvious that there is more generation than the consumers can pay for, noting that the solution is for the stakeholders to look for the customers that are not well served under the Eligible Customers Regulation to take it and pay for it for their benefits.

    Read Also: FG may convert seized properties to museum

    He submitted that “if we do this aggressively, that 2,000mw of so-called stranded generation will quickly evaporate.”

    He told the stakeholders to look for customers to buy the stranded power because it is inappropriate for government to continue to pay for the power.

    According to him, government cannot perpetually pay for their power consumption.

    Edozein also told the Transmission Company of Nigeria (TCN) to stop the complaint about non-increase of tariff to the NERC and work with the GenCos to get willing customers to buy the available power.

    He said that “I have a message also for TCN: stop complaining to NERC about your tariff. Your job is to satisfy your own customers that is GenCos and DisCos.

    “Work with them as you have the money to find all customers using this policy who will take the power GenCos have, contract with GenCos at a tariff that you, the GenCos and customers agreed to transmit the power close to the customers. That is the way you will raise your revenue.”

    The Permanent Secretary urged the DisCos to satisfy their customers in order to encourage them to pay for the service.

    He explained to the DisCos that the reason the customers would want to take advantage of the eligible customer regulation is when they are not satisfied with the services rendered to them by the DisCos.

    He said “So DisCos this is your opportunity to service your customers better. Listen to them when there is infrastructure challenge in getting the product to them.”

    There was however a mild drama as the Deputy Managing Director, Ibadan Electricity Distribution Company, Engr. John Ayodele counted the Permanent Secretary on stranded 2,000mw.

    He told the stakeholders that there is no stranded 2,000mw anywhere in the Nigerian Electricity Supply Industry (NESI) but the Executive Director, Mainstream Energy Solution Limited, Mr. Siraj Abdullahi, insisted that his company, Kainji Power Hydro habours some stranded power.

    He challenged the stakeholders to come visiting the plant to observe the stranded power.

  • ‘TCN has achieved grid stability’

    To Transmission Company of Nigeria (TCN) Managing Director, Mr. Mohammed Gur Usman, the commission has achieved stability in power transmission. But distribution has been epileptic, according to him, because distribution companies (Discos) were sold to inexperienced operators. He speaks with John Ofikhenua and Moses Emorinken on this and many other issues.

    Can you give us an update on the affairs of the West African Power Pool (WAPP) after your meeting in Abuja last month?

    I am the Chairman of the West African Power Pool (WAPP). I believe the last meeting we had in Abuja was on the frequency control because the Transmission Company of Nigeria (TCN) wrote to WAPP and asked for the synchronisation of the network so that power can flow in these three islands. We have three islands now where the power are landed because of the problem of frequency, and  that was why we wrote to WAPP and asked them to synchronise. WAPP sought and got the support of the World Bank to finance a committee that would do the synchronisation programme. They organised series of workshops. One of the workshops was what took place here in Abuja. It was sometime in December. At that workshop we took a decision to take all the steps that we needed to ensure that we have a synchronised grid. That will require us to meet the frequency control of the WAPP  standard, which are 49.2Hz and 50.2Hz. The intention is that if the utilities can achieve 60 per cent of that standard, then we can synchronise. At the point of the meeting, Ghana and other islands, which involves Côte d’Ivoire, have met that standard. We could have synchronised with them if we also achieved the standard. A day after the workshop, I set up a committee, which reported directly to me and charged them to work towards the achievement of the WAPP standard. I am happy to tell you that, if you look at the frequency control, from three weeks ago till date, the frequency is between 49.8Hz and 50.2Hz for 75 per cent of the time, which is far above the Ghana signal. This is the best in West Africa so far now. We have never achieved this in the history of Nigeria. So, what  we are working on is not only to expand the grid, but to ensure that there is stability of the grid. So, that is what we achieved in the last workshop, which held here in Abuja.

    What is your  relationship with supply of power to neighbouring countries? Has there been a review due to non-payment of outstanding bills?

    Our relationship is that we wheel power across and outside the country. We take energy outside Nigeria. Currently, we have two or three points where we supply energy to Niger from the Northern part. One of them is through Maiduguri to Damasai and then through Doso. That one is not working now because the network was destroyed by the terrorist element of Boko Haram. The supply is done at the level of distribution companies (DisCos). It is not at our level. It is Yola DisCo that supplies that energy. The next one is the one we supply to Niger through Katsina. It goes to a town called Maradi and Doso. That one is 60Mw of electricity that we send on a daily basis to Maradi and Gazawa. The next one is the one from Birnin-Kebbi to Yamai and this is 120Mw, and on a daily basis we send this energy to those places. The other point where we send energy to outside Nigeria is through Ikeja west to Sakete. For this we are sending the following power: 200Mw to  Community Electric du Benin (CEB) under the agreement we have signed with them, which is a bilateral agreement between the government of Nigeria and the government of Benin and Togo. The other one is the 60Mw that we send to Societe Beninoise d’Energie Electrique (SBEE). SBEE is the electric distribution company of Benin Republic. We have been sending it on a consistent basis. Concerning the issue of payment, I think we have very little problem with Niger, their payment is always up-to-date. Where we have significant problem is on the CEB side, but we have agreed with them on how they are going to liquidate the payment, and I think they are making serious efforts to make all the payments. The one that is Paras Energy is the bilateral agreement between Paras and SBEE. As far as I am concerned, I believe the payment is up-to-date, because Faras is not owing TCN for the payment of transmission charges. So, that is where we are now as far as international customers are concerned.

    Sometime in 2017 you sent a request for an increase in extraordinary tariffs to the Nigerian Electricity Regulatory Commission (NERC), what do you think is responsible for the delay in approval, and how has it affected TCN’s operation ?

    When we newly came in , we did a presentation to Nigerian Electricity Regulatory Commission (NERC), with a compelling reason that showed that TCN is underfunded. The NERC agreed that we should come and present a case for extra-ordinary tarrif review, this was in 2017. We sought and got the support of Power Africa, which gave us some consultants that support our staff to prepare the case for extra-ordinary tariff review, which we did. We submitted to NERC, and there was a tentative agreement with NERC that our tariff is low and that it should go up. There were a few points of disagreement, but since that time we have not heard anything from NERC.

    I think it will be interesting if you can go and speak to NERC why they have not done it. We need extra-ordinary tariff review to be able to operate TCN and to meet our own liability. If you remember, the Transmission Expansion Rehabilitation Programme under which we sought and got support from international donors, TCN is going to repay all those loans, and we are going to pay it through the wheeling  charges that we have. So, definitely, we require the NERC to act on this. If you look at the industry now, there is none that is as hard working as the TCN. TCN’s engineers are the most hardworking staff you can see. We have become the game changer. Remember, this is the same TCN that was believed that you need to bring foreigners to manage it. Manitoba Hydro was brought here to manage this place, and in four years that they were here, Manitoba did not bring a single investment into TCN. Nigeria (officially) paid Manitoba Hydro $32million for managing TCN. For the four years that they managed TCN, they did not carry out a single audit of TCN. For the frequency control I just told you, one of them has sent an email to me to congratulate us for achieving it, saying that this is something they contemplated of achieving, but they could not. They could not even come close to it.  So, all these things we are doing, I think there should be some motivation on the side of government and the regulator. But if you look at it now, TCN is the least paid in the industry. I don’t think it makes sense because we operate high voltage. Look at it from the point of risk, TCN is exposed to more risks than anyone in the sector. I think I will be happy if from your side you can put pressure on the government, the regulator and find out from them why they are not approving our extraordinary tariff review.

    What is TCN’s wheeling capacity?

    You have to give credit to this government for some of the actions they took, including reconstituting TCN management. I remember that they inherited all those structures from the previous government and some of the decisions they took, including bringing someone like me to come on board to see how we can fix the power sector. When we came in February 2017, the capacity of TCN was around 5,000Mw. As at December 2017 when we simulated the grid, it was 7,124Mw. The last simulation which we did in December 2018, the capacity of the grid was 8,100Mw. We are on track to moving the grip to at least 20,000Mw by 2021. These are some of the achievements that we have recorded. Also, we have installed more transformers in the last one and half years to two years, more than what was done in previous 15 years. How did we do it? We met stranded containers of about 800 at the port; some of them had been there for over 15 years. Some of them had been auctioned. Manitoba was just looking at those things and did nothing to them. As at now, we have recovered 708 of the 800 containers, and we have also come up with strategies to remove the remaining ones.

    Some of the equipment recovered will encourage TCN engineers to do the installations themselves. In many cases, the TCN engineers do the installations at the rate of 10 per cent of the time that we normally spend on contractors, and at the rate of about 10 per cent of the money that we normally spend on contractors. This is where we achieve so much more than what has been achieved in the past. I can tell you that it is sustainable, and they are not doing below standard work. In reality what we discovered is that most of the contracts executed in the past  were done by TCN staff. So, we decided to empower them directly, and because they are using TCN engineers, who work for TCN most of the time, they don’t work on weekend and public holidays. That is why it takes long time for them to finish the job. But now they are doing it directly and we are achieving a lot of results. We have also decided to support contractors that are doing well, and are willing to work with us and are not willing to fight us. We enter and  support them to complete the project and pay whatever we owe them. But we have stopped variation of that kind of contracts. That is how we were able to finish Kukwaba here in Abuja. That is how we were able to finish the first segment: Katsina, Daura 132kv line and several others. Last week we entered Gagarawa and we are going to complete Gagarawa like that.

    There are some contractors that don’t want to cooperate with us. They want to continue to stay in the old regime. For your information, before the coming of Buhari administration, most of the contracts given in the power sector were not given with the hope of completing them. The objective was to empower people and make them rich. And that is why capacity and experience do not matter. You see some people, who have never done the project they give them. Some of those projects have been funded 100 per cent, LC money removed from them and you cannot see the material commensurate with the money that has been paid: no erection, nothing.  I can give you example of one of these.

    For example, the 330 KV line from Alaoji to Owerri, Owerri to Ihiala, from Ihiala to Onitsha was given like that, and there is nothing on ground now. Now, the government is going to borrow to build that line again after it was given to some people and they abandoned it. Such contractors that have refused to complete their work, we sometimes enter forcefully, take over the job and complete it. I, also can tell you that no contractor took us to court and succeeded because we are very good in project management. We understand how to intervene, and how to enter and take over. So, when we are cancelling such contracts that have such problem we don’t validate them. We leave them where they are. When we are cancelling we say we are not understanding so there is no contract for you to see us for. This is how we were able to forcefully take over Damaturu. Precisely, Damaturu was awarded in 2006, with a completion period of 24 months. As at last year up to June, Damaturu was not completed; so we forcefully entered and completed the project. It is supplies at 330KV now. Invariably, by completing Damaturu, Maiduguri, which  was actually completed but because Damaturu was not completed was not supplied, Maiduguri got supply. I can tell you in the Northeast now the government of President Muhammadu Buhari  has put 100 per cent capacity of power in the Northeast. Before now, the whole of Northeast had only two 330KV substation in Yola and Gombe. Now, we have another 330KV in Maiduguri and Damaturu. We also took over Wudil and completed it. Next week we are going to commission it. We also took over Yauri. It is going to be completed in the next one or two weeks. They have started the pre-commissioning test. We have forcefully taken over Nineth Mile in Enugu State and we are going to complete it. So, this is how it is. I can tell you that no contractor holds us to ransom now. I can also tell you that TCN engineers are building a 132KV substation in Lagos on an island called Ilase; they are the one carrying every equipment to the sea and the job is 98 per cent completed.

    Is your penchant for engaging in-house engineers generating any bad blood in the industry?

    Why should it generate bad blood? When contracts are not working, there are people benefiting from it. Those people who are benefiting from it would be angry, of course. If a system is not working, it is the majority of the people that will suffer. So, you have included those few people who are not benefiting and supported the majority of the people that are benefiting.

    There was an assessment pool done by either China, where they did a population poll; more than 70 per cent of Nigerians say their lives have improved with the improvement of power supply. I think it is important. What is more important is that we have created a system where TCN engineers are testing their capacity. No nation should be depending on foreigners and other people. So, we are building the capacity of our people.

    Why is distribution still low (between 4,000Mw to 5,000Mw) despite the increase in generation between 7,000Mw and 8,000Mw?

    I will tell you that the kind of privatisation that was done by the previous government has never been done in any part of the world. If you ask the people who did the privatisation, they will tell you that they used the Indian model. The Indian privatisation model is such that they privatised one state called the state of Orisa. It is the experience from the state of Orisa that they used to privatise Delhi. In the industry, the most important segment you have to work properly is the distribution because they are the one that collect the money. It is the money from distribution that is supposed to go to all other places. So, they  privatised state of Orisa and the experience learnt from it is what they used for Delhi. Nigerians have this report, but we went and sold everything at the same time and put a continual  liability of $5.4 billion. So, what most people don’t know is that when they are gauging Buhari administration, they are gauging it from the point of what it has achieved. Nobody is looking at the hole that the previous administrations put Nigeria into. This is what this government has inherited. Now the option of cancelling the privatisation is the option of paying $5.4billion

    I agree with this government that they didn’t tamper with the reform of previous government, if they had done that, it will also send a wrong signal to the international community that the government is against reform. But the government has done a lot of work. The privatised segments are generating but   generation is no longer a problem. Transmission was the weakest link in the power value chain. It was also the biggest problem in the power value chain. But today, it is no longer the problem. We are not saying transmission has solved all its problems, but anywhere we have problems, at least, we have a plan to fix it. We are working on putting nil contingency across the country; meaning any part of Nigeria where one line or equipment goes out, it should not affect the supply. That is consistent with the transmission expansion programme that we are doing, and that is the standard worldwide and we are on track.  What remains is the last mile, which is the Discos. If you remember, the government also came out with N72billion investment in DisCos, which TCN is in charge of managing the investment. We are actually working to stabilise the DisCos. I also want to assure you that every step to stabilise the DisCos is being taken by this government and I am telling you that in the next level that is where we are going to fix it.

    Are you still calling for the recapitalisation of the DisCos?

    Of course, that is what is required. Government has recapitalised TCN; we have raised $1.623bn so far in investments in transmission, so DisCos need to recapitalise. There is need for them to find the regulatory and policy environment that will force this recapitalisation of the DisCos. Let me tell you why the DisCos have to recapitalise. When we did the simulation with the Transmission Expansion Rehabilitation Programme, we also simulated up to 33KVA network, and the finding is that for the DisCos to pick successfully the load we have and put all the required protection, they need at least $4.2bn worth of investments for them to successfully take the power. Where will that money come from? The money is supposed to come from recapitalisation. I also want to tell you that some of the mistakes we have made in the past. Infrastructure financing requires long term finance. Part of the problem we have with the DisCos is that most of the funding that they have came from  commercial banks, which are short term in nature and very expensive. We need funding that will have repayment period of at least 10 years moratorium period; you can’t get it from financial market. So, we are not talking about recapitalisation by bringing all those short-terms. Short terms are expensive and they will not be able to build the infrastructure successfully. If you look at our interface now, we have 738 interfaces across the country. Out of these 738 interfaces we have only 421 that are fully protected. What do I mean?  Only 421 are the distributions that have their own injection substations. You know the power industry works with what you call protection and that is why if you go to your house you have what is called ELCB. If you have a problem in your house it will trip. That is the nature of power work. If your house doesn’t trip it will  burn the transformer. So, all of them need to work and if they don’t work there is going to be a problem.  The remaining interfaces, some  have protection, some don’t have. For the balance of 179 there is no protection at all. In recent times we have been having problems with our transformers in some stations. In Abuja, in Karu we lost one transformer, we have replaced it. In Kubwa, we also lost a transformer. In Benin we had two not too long ago. We have one in Onitsha. All are those networks that are not protected meaning faults in people’s house can come and hit our transformers. So, that requires investments. They have to put investments to be able to do this. This is the existing infrastructure and we are moving it from 8000mw to 20,000Mw. So, even TCN investments cannot be protected if we don’t have significant investments in DisCos.

    What is the level of demand for power?

    The fact is that transmission has a capacity of 8,100Mw, and generation has a capacity of 7,500Mw, and the DisCos can pick only 4,000Mw – 5,000Mw. That is what you will generate; you can’t generate more than that. So, we need to fix the last mile to ensure that we optimise the use of electricity and all the efforts are being made. We are expanding generation and we have  every plan to make generation work. Most of these power plants, we are rehabilitating their capacities. Mainstream is expanding Kainji and Jebba. So, they are putting what is called floating solar. You know about Zungeru, it is going to be completed before the end of this year or early next year, and that is 700mw.  Mambilla, which we have been talking about for several years has been resolved. We also have to give credit to this government. Any other thing you read in the papers are all lies. We have got approval to evacuate Mambilla through the Eastern Backbone. You heard about the QIPP, you heard of Agip, it is doing phase two, which is going to be about 510mw.  All these are coming on board. Transmission is outstanding. We are building network. We are even building a cord line, which has never happened in the history of this country. That is going to be double of the circuit line.

    Benin Electricity Distribution Company (BEDC) says its problem with its customers that are complaining has to do with TCN. What do you say to this?

    I don’t know which location they are saying but you know that Benin DisCo admitted that one of the last transformers that got spoilt in Benin was caused by them. They even wrote to us to say that they are willing to fix it. The point is that do you fix a transformer in one day?  So, we have to carry a transformer from somewhere and fix it. The problem we have with most of the distribution companies is that we sold our companies mostly to those that have no experience.   And they don’t have capacity to raise enough investments. Of course, there are also some issues that   have to do with tariff which the government has not completely fixed.  But I can also tell you that many of them are operating auto-closers, where they are also keeping people outside the supply. Except you can tell me which specific place. But I can tell you generally that we have enough supply that Benin is not taking.  As I told you, it is not as if there are no places we have problems. There must be one or two places where we have problems. But I told you anywhere we have a problem we have a plan of fixing it. So passing the buck like that doesn’t make sense. If there are specifics let us know. I can tell you we are on top of our plans.

  • TCN, AEDC trade blame over load allocation, rejection

    The Transmission Company of Nigeria ( TCN ) and Abuja Electricity Distribution Company (AEDC) on Friday traded blames over why power supply to the DisCos and customers was low.

    TCN’s Managing Director Usman Gur Mohammed said there was no network constraint in the Nigerian Electricity Supply Industry (NESI) that would have amounted to load reduction.

    The TCN boss spoke at the official commissioning of 2*60 power transformers in Suleja Transmission Substation, Niger State.

    According to him, the constraint was simply that of the AEDC equipment.

    He promised to take the reporters on a tour on the transmission substations around within the territory of the AEDC.

    He said: “The constraint that Abuja has is within their equipment not within the network.

    “And there is no place in Abuja where we have the network. Let me tell you, some of the things we did in Kano, Kaduna, if you are interested we can take you.

    “In Kaduna they created this problem and said we have problem with network, I instructed our regional manager and said take them to the sub-station and show what was the capacity and what distribution were taking.

    “So, we will do the same thing for you to enter our sub-station in Abuja so that you can see for yourself what is the capacity there and what has Abuja DisCo taken.”

    But AEDC Head of Corporate Communications Oyebode Fadipe told our correspondent on phone although the AEDC had its challenges, it was unfair for the MD of TCN to blame all the constraints in the sector on it since there were also challenges of transmission network.

    He said: “It will be unfair to say that it is our company (AEDC) that made our customers not to have power in the homes.

    Read Also; TCN targets 20,000 megawatts in 2021, says MD

    “We have our challenges and TCN has its own constraints too, it is unfair for him to keep saying that the DisCos are the weakest link in the value chain. TCN should face its challenges and let us face our own.”

    The Nation, however, learnt from a source who did not want her name mentioned that “in this week, the breaker in Gwagwalada was bad. The line in Kukwaba, Kubwa tripped off.”

    The sources wondered whether those faults were those of AEDC equipment.

    The commissioned transformers, according to TCN, were from the $100million loan intervention that the Federal Government received from the International Development Association.

    The contract was awarded to Messrs MBH Power limited in June 2016 with a completion date of June 2018.

    The transformers that have load capacity of 48mw to 162mw will increase the substation’s capacity from 66mw to 162mw.

  • Faulty transformers: KEDCO boss appeals to customers

    Managing Director and Chief Executive Officer of Kano Electricity Distribution Company ( KEDCO ) Dr Jamilu Gwamna has appealed to customers to be patient as repair work on faulty transformers were on-going while assuring them of better power delivery as soon as the transformers were fixed.

    Gwamna said this in Kano on Monday while fielding questions from newsmen following an SOS sent by customers to Transmission Company of Nigeria (TCN).

    According to him, it has become imperative to issue such appeal as it is one set-back that is currently threatening our good relations with our numerous customers who have taken their complaints to even the TCN aside the similar ones made to KEDCO.

    “It has come to the level that we have to beg our customers who are affected by the faulty transformers because we don’t want anything to dent our relationship with our customers as it is tilting towards.

    “Our customers have been good and faithful in their payments. The truth is that we didn’t cause this and we don’t pray it continues this way but I assure our customers that better days wait them in terms of power delivery as soon as the transformers are fixed.

    “We are aware that some of our customers are not happy especially those that are directly affected. But I can assure you that the TCN and KEDCO are working to get things back online. So, let the customers exercise patience.

    The Kano DisCo boss emphasized that the customers are the ones keeping them in business, adding that their happiness must be sought.

    He appealed to the TCN to quicken repair works on the faulty transformers while assuring the customers that succour would still come to them when the transformers become functional.

    Gwamna also appealed to the youths of host communities where KEDCO installations are to report any slight change in the position or sound of such equipment.

  • TCN: $5.4b refund way out of privatisation

    The Transmission Company of Nigeria (TCN) has said the refund of $5.4billion is the only option left for the Federal Government to pull out of the privatisation of the power sector.

    It said globally, India is the only country that has ever adopted the Nigerian model of privatisation in selling the assets of the defunct Power Holding Company of Nigeria (PHCN).

    Its Managing Director, Mr. Mohammed Gur Usman, said Nigerians were scoring the President Muhammadu Buhari-led administration on what is on ground, forgetting about the problems created by previous administrations. “Nobody is looking at the hole that the previous administrations put Nigeria into. This is what this government has inherited. Now, the option of cancelling the privatisation is $5.4billion,” he told The Nation in Abuja.

    The management of the power firm has already reached out to Ogun State government as high compensation demand for the right of way (RoW) has stalled the $200million transmission project.

    He added that the project was being financed by the Japanese government through its Japanese International Corporation Agency (JICA).

    He said it was expected to address the power transmission challenge between Ogun and Lagos states and wheel power to the highly industrialised axis.

    But what is delaying the project, according to the TCN boss, is that the demand for compensation for the right of way is too high.

    He said: “This project has been completed and we have done the design, but what is stalling the project is that the compensation for the right of way is too high. So, we are working with Ogun State government through collaboration where they are working to reduce the cost.”

    He said the project, the first of its kind, is for the installation of four 330KV substations between Lagos and Ogun.

    “We are putting four 330KV substations between Lagos and Ogun. For your information, this is the first time in the history of Nigeria that more than one 330KV substations are being built in the same location,” he said.

    Usman, however, revealed that once the company settles the compensation of right-of-way issue with the state, it will advertise the project.

  • TCN eyes 20,000Mw by 2021

    The Managing Director, Transmission Company of Nigeria (TCN), Mallam Usman Gur-Mohammed said the company is on track to deliver its 20,000 megawatts (Mw) target by 2021.

    Speaking yesterday in Kano, he said President Muhammadu Buhari has done alot  of work to support the company in the areas of transmission and expansion programme, which brought about the transmission network from 5,000 Mw in 2017 to 8,100 Mw it currently is.

    According to him, the firm has achieved the level that has never been achieved in the history of the power sector. “As l speak to you now, our frequency control is the best in west Africa.This has never happened; we focus mostly on expansion, not looking at the the quality of the power. But now we are not focusing on expansion and the quality of the power,” he said.

    He spoke while fielding questions from newsmen shortly after inaugurating the 1×60 MVA 132/33KV transformer at Dan’agundi transmission substation Kano.

     

  • TCN gets approval to evacuate power from Mambila

    The Transmission Company of Nigeria (TCN) yesterday said it has received an approval to evacuate power from the Mambila Hydro Power Plant.

    Its Chief Executive Officer, Mr. Mohammed Gur Usman, who spoke on development described the power project as part of the West African Power Pool (WAPP) projects.

    He said: “We have got approval to evacuate Mambila through Eastern Back Bone.”

    Speaking with The Nation in Abuja, he said the approval was got December 22, last year at the meeting of Heads of States of the Economic Community of West African States (ECOWAS).

    He said there was an approval of the updated version of the WAPP 2018 Master Plan of priority projects.

    The TCN chief one of the priority projects starts from Calabar and ends in Kano.

    He said: ” One of the priority projects is the Eastern Backbone which will start from Calabar and end in Kano. It is 330KV double socket. That project will enable us to connect with Central African Power Pool through Ikom. It will also send power to the most neglected parts of Nigeria.”

    The most neglected parts, according to him, are northern Cross River and Taraba states.

    He said the Mambila project has come up with an updated study for energy to be evacuated from where it is cheaper to where it is more expensive.

    Nigeria, he said, is the largest trader of electricity in West Africa and the updated study is seeking to evacuate energy to Central African Power Pool and North Africa Power pool.

    This according to him, requires transmission line in the east of Nigeria.

    He said the Benin axis has enough of power that the Benin Electricity Company (BEDC) is no demanding for.

    He said: “I can tell you generally that we have a lot of power that BEDC is not taking.”

    According to him, most of the distribution companies were sold to firms that lack experience and capacity to raise sufficient investments.

    The TCN chief, who said two transformers were blown-up in Benin two months ago, said the Benin DisCo admitted that one of the last transformers that sparked there was caused by them.

    “Benin DisCo admitted that one of the last transformers that got spoilt in Benin was caused by them. They even wrote to us to say that they are willing to fix it. The point is that: Do you fix a transformer in one day?  So we have to carry a transformer from somewhere and fix it .

    “The problem we have with most of the distribution companies is that we sold our companies to mostly to companies that have no experience.  And they don’t have capacity to raise enough investments.”

    He said the Nigeria Electricity Regulatory Commission (NERC) should approve an extraordinary tariff review for the operation of the company.